ANP Bellingham Energy Project is a natural-gas combined-cycle station in Norfolk County, Massachusetts, associated with ISO New England. The EIA plant baseline lists 578 MW of nameplate capacity. A FERC asset appendix lists two 289-MW units placed in service in November and December 2002. The Massachusetts Energy Facilities Siting Board approved a proposed 580-MW nominal-net project. The profile keeps the EIA nameplate, FERC unit, and state-approved nominal-net figures distinct.
Mapped infrastructure geometry associated with this asset.
EIA plant 55211 · Inventory for Aug 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| U1 | Natural Gas Fired Combined Cycle | Operating | 289 | Unknown |
| U2 | Natural Gas Fired Combined Cycle | Operating | 289 | Unknown |
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| U1 | 289 MW 258.1 MW summer | Natural Gas Fired Combined Cycle Natural Gas · CS | Nov 2002 | Operating |
| U2 | 289 MW 262.1 MW summer | Natural Gas Fired Combined Cycle Natural Gas · CS | Dec 2002 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Project milestones and public references behind the asset profile.
The FERC asset appendix lists one 289-MW unit in service in November 2002.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
The FERC asset appendix lists the second 289-MW unit in service in December 2002.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
ANP Bellingham Energy Project reports 578 MW natural gas of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Aug 2026.
ANP Bellingham Energy Project is a Natural Gas Fired Combined Cycle facility in Norfolk County, MA, participating in the ISO-NE market.
ANP Bellingham Energy Project is in Norfolk County, MA, inside the ISO-NE balancing area.
ANP Bellingham Energy Project is operated by Bellingham Power Generation LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
ANP Bellingham Energy Project reported 2,801.4 GWh over the twelve months to 2026-07. Figures are net generation as filed to EIA-923.
By capacity, ANP Bellingham Energy Project ranks #268 of 540 operating plants of the same technology nationally. It ranks #3 of 15 in MA.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.