Bitter Blue Campus
Proposed
Proposed
Amazon Data Services owns and Amazon Web Services operates the proposed Bitter Blue Campus at 12807 Donop Road, San Antonio; Building B, a permitted two-story single-tenant data center, is scheduled for construction start December 2026 and completion February 2029 with an estimated cost of $65 million. No capacity, data-hall area, or power figures are disclosed; the facility is not documented as under construction or operational as of July 27, 2026.
Building B at the Bitter Blue campus, 12807 Donop Road, is identified as a new two-story, single-tenant computer-data-center building filed by Amazon Data Services. The TDLR record lists an estimated cost of $65 million and scheduled construction dates. No capacity, data-hall area, commercial-operation date, or actual-online date is provided.
Also reported as BITTER BLUE, Amazon AWS SAT - 12807 Donop.
Reports that Amazon plans a $65 million data center on San Antonio's Southeast Side at 12807 Donop Road, with construction scheduled from December through February 2029.
Reports that Amazon Web Services filed for the Bitter Blue data-center project at 12807 Donop Road. The project is described as a roughly 120,000-square-foot, two-story, single-tenant facility costing about $65 million, with completion expected in February 2029.
Reports that Amazon plans a Southeast Side data center at 12807 Donop Road, identifying Amazon Data Services Inc. as the owner and citing a $65 million estimated cost and February 2029 completion date.