Cavalry Solar
Cavalry Solar Hybrid reports 45 MW battery storage + 200 MW solar in MISO.
Cavalry Solar Hybrid reports 45 MW battery storage + 200 MW solar in MISO.
EIA plant 67489 · Inventory for Aug 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| CAVBS | Batteries | Operating | 45 | 180 |
| CAVPV | Solar Photovoltaic | Operating | 200 | Unknown |
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| CAVBS | 45 MW 45 MW summer | Batteries Electricity used for energy storage · BA | May 2024 | Operating |
| CAVPV | 200 MW 200 MW summer | Solar Photovoltaic Solar · PV | May 2024 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Project milestones and public references behind the asset profile.
EIA-860 lists generator CAVBS, generator CAVPV with this operating date.
Completion announced by NIPSCO
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Cavalry Solar reports 45 MW battery storage + 200 MW solar of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Aug 2026.
Cavalry Solar is a Batteries, Solar Photovoltaic facility in White County, IN, participating in the MISO market.
Cavalry Solar is in White County, IN, inside the MISO balancing area.
Cavalry Solar is operated by Cavalry Energy Center LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Cavalry Solar reported 366.6 GWh over the twelve months to 2026-07. Figures are net generation as filed to EIA-923.
By capacity, Cavalry Solar ranks #152 of 7,597 operating plants of the same technology nationally. It ranks #6 of 126 in IN.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.