CleanSpark Sandersville
Expanding · CleanSpark · 2015 George Lyons Parkway, Sandersville, GA
CleanSpark Sandersville, at 2015 George Lyons Parkway, is a Bitcoin mining campus CleanSpark acquired from Mawson Infrastructure Group in October 2022. In July 2026 CleanSpark signed a 20-year lease with an undisclosed high-investment-grade technology company for 175 MW of critical IT load, with deliveries expected from Q4 2027. Construction is under way, funded by $2.276 billion of senior secured notes.
Loading map…
Overview
- Campus power
- 175 MW
- Critical IT Load · Reported
- Status
- Expanding
- Expanding campus
- IT floor area
- Not disclosed
- Campus
- Compute profile
- Crypto Mining · AI HPC
- Cooling design
- Reported
- air cooling
- Project scope
- Campus at 2015 George Lyons Parkway, Sandersville, GA.
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 175 MW | Critical IT Load | Reported | HPC lease | — |
| Critical IT load leased for 20 years to an undisclosed high-investment-grade technology tenant; deliveries expected to begin in Q4 2027. | ||||
| 100 MW | Energized Power | Energized | 150 MW mining expansion | — |
| First 100 MW of the 150 MW Bitcoin mining expansion energized. | ||||
- Utility
- Municipal Energy Authority of Georgia (MEAG)
- Substation
- MEAG 200 MW substation serving the Sandersville expansion
Facility and development
- Facility class
- Crypto Mining · AI HPC
- Cooling systems
- air cooling
- Operating context
- Bitcoin mining in air-cooled buildings since October 2022; a 20-year triple-net lease for 175 MW of critical IT load was signed in July 2026, with construction under way.
- Transactions
- Acquired from Mawson Infrastructure Group, effective October 8, 2022 · 20-year triple-net lease with an undisclosed high-investment-grade technology company, about $6.6 billion of contracted revenue (July 2026) · $2.276 billion of 7.875% senior secured notes due 2031 closed by CSDC Finance I, LLC to fund the build-out (September 2026)