Cologix COL3
Operating · Cologix · 585 Scherers Court, Columbus, OH
Cologix COL3 is a 160,000 sq ft colocation data center at 585 Scherers Court in Columbus, Ohio. Cologix describes it as a $130M+ Scalelogix facility linked to its COL1 and COL2 data centers and as the largest neutral data center in the region. It holds an Uptime Tier III Certified Constructed Facility designation and is described as concurrently maintainable.
Overview
- Exact-site power
- Not disclosed
- No exact-site MW figure in cited sources.
- Status
- Operating
- Operating facility
- Facility size
- 160,000 sq ft
- Facility
- Project cost
- $130.0M
- Estimated construction cost in the cited project filing.
- Compute profile
- Colocation
- Project scope
Power and grid
- Redundancy
- Concurrently maintainable
Facility and development
- Gross floor area (sq ft)
- 160,000
- Facility class
- Colocation
- Availability tier
- Tier III
- Project cost (USD)
- 130,000,000
- Grid record