Core Scientific Dalton 1 & 2
Operating
Core Scientific's Dalton 1 & 2 site at 2205 Industrial South Rd occupies about 5 acres with 52,000 square feet. Dalton Utilities supplies power. The land is leased from the Dalton-Whitfield County Joint Development Authority under a bond-financed sale-leaseback for tax abatements.
Loading map…
Overview
- Status
- Operating
- Operating facility
- Compute profile
- AI HPC · Crypto Mining
- Project scope
- Dalton 1 is being converted from bitcoin mining to HPC and AI workloads under a T5 Construction contract, expected substantially complete in the first half of 2026.
- Power and grid
- Served by Dalton Utilities.
- Compute role
- AI HPC, Crypto Mining.
Power and grid
- Utility
- Dalton Utilities
- Nearest substations
- Unnamed substation115 kV
- Unnamed substation230 kV
- Point of interconnection
- Not identified
Facility and development
- Construction
- Dalton 1 is being converted from bitcoin mining to HPC and AI workloads under a T5 Construction contract, expected substantially complete in the first half of 2026.
- Facility class
- AI HPC · Crypto Mining
- Tax abatements
- Bond-financed sale-leaseback with the Dalton-Whitfield County Joint Development Authority for tax abatements
- Utility agreements
- Amended and Restated Electric Service Agreement with the City of Dalton Board of Water, Light and Sinking Fund Commissioners, dated October 11, 2018 (Industrial South Premises)