Csquare Watertown BOS4 Data Center
Operating · Csquare · 486 Arsenal Way, Watertown, MA
Csquare operates its Watertown BOS4 data center at 486 Arsenal Way in Watertown, Massachusetts, about 10 miles from Boston Logan International Airport. The operator reports 19.1 MW of utility capacity, 4 MW of UPS capacity and 14 MW of generator capacity, with chilled-water cooling. The site is carrier neutral with 12 connectivity providers.
Overview
- Exact-site power
- 4 MW
- UPS capacity · Reported
- Status
- Operating
- Operating facility
- IT floor area
- Not disclosed
- Facility
- Compute profile
- Colocation
- Project scope
- Facility at 486 Arsenal Way, Watertown, MA.
- Power and grid
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 19.1 MW | Capacity basis unspecified | Reported | Exact Asset | — |
| Operator-reported utility capacity; basis unspecified. | ||||
| 4 MW | UPS capacity | Reported | Exact Asset | — |
| Operator-reported UPS capacity. | ||||
| 14 MW | Capacity basis unspecified | Reported | Exact Asset | — |
| Operator-reported generator capacity; basis unspecified. | ||||
Facility and development
- Facility class
- Colocation
- Cooling medium
- Chilled water
- Fiber and connectivity
- Carrier neutral, 12 connectivity providers; Csquare Digital Exchange enabled.
- Grid record
- Interconnection not publicly disclosed