DataBank IAD3 Data Center
Operating
DataBank IAD3 Data Center is a DataBank-operated facility at 21630 Red Rum Drive in Ashburn, VA.
Loading map…
Overview
- Exact-site power
- 40 MW
- Critical IT Load · Reported
- Status
- Operating
- Operating facility
- IT floor area
- 200,000 sq ft
- Facility
- Compute profile
- Colocation
- Cooling design
- Reported
- N+1 Cooling Design · Air cooling (10kW+ cab density) · Liquid cooling (25kW+ cab density)
- Project scope
Power and grid
- Utility
- Dominion Energy Virginia
- Substation
Off-site utility-owned substation providing 70 MW to the Ashburn campus
- Nearest substations
- Unnamed substation230 kV
- Greenway230 kV
Facility and development
- IT floor area (sq ft)
- 200,000
- Construction
- IAD3 opened in 2023 as the newest addition to DataBank's 18-acre Ashburn Campus, expanding the campus to 355,000 IT square feet.
- Facility class
- Colocation
- Cooling systems
- N+1 Cooling Design · Air cooling (10kW+ cab density) · Liquid cooling (25kW+ cab density)