DC BLOX Atlanta East Data Center Campus
Under Construction
Under Construction
The DC BLOX Atlanta East campus is a hyperscale data center campus at 1726 Farmer Road in Conyers, Rockdale County, Georgia. The operator lists it as partly operational and partly in development, with Building 1 completion celebrated in March 2026. DC BLOX lists 154 critical MW across completed and planned buildings, served by Georgia Power. Backup power is diesel emergency generators; no dedicated onsite power plant is documented.
Completion celebrated by the operator in March 2026
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 154 MW | Critical IT Load | Reported | Exact Asset | — |
| Critical power across completed and planned scope; not confirmed energized load | ||||
| 216 MW | Utility Service | Contracted | Exact Asset | — |
| Full build-out total power committed by Georgia Power | ||||
| 144 MW | Critical IT Load | Reported | Exact Asset | — |
| Earlier operator overview of the campus configuration | ||||
| 10 MW | Capacity basis unspecified | Reported | Exact Asset | — |
| One building in the operator's four-building configuration | ||||
| 48 MW | Capacity basis unspecified | Reported | Exact Asset | — |
| Each of three buildings in the operator's four-building configuration | ||||
| 30 MW | Capacity basis unspecified | Proposed | Exact Asset | — |
| Building in the regional review site plan; not additive to later configurations | ||||
| 80 MW | Capacity basis unspecified | Proposed | Exact Asset | — |
| Building in the regional review site plan; not additive to later configurations | ||||
| 40 MW | Capacity basis unspecified | Proposed | Exact Asset | — |
| Building in the regional review site plan; not additive to later configurations | ||||