Delta Energy Park is a 250 MW natural gas-fired combined-cycle plant in Delta Township, Michigan, owned by the Lansing Board of Water & Light. The roughly $500 million plant broke ground in June 2019 and entered service in March 2022, replacing coal generation at the Erickson site. It has three Siemens Energy combustion turbines and a Doosan Skoda steam turbine. In 2024 BWL sued Siemens Energy over turbine reliability.
Overview
- Registry anchor
- Plant 63259
- plant-63259
Infrastructure record
- Mapped facility footprint
- Mapped infrastructure footprint
Mapped infrastructure geometry associated with this asset.
- In service
- 2022-03