Equinix Ashburn DC15
Operating
Operating
Equinix Ashburn DC15 is a building data center in Ashburn, Loudoun, VA. Equinix, Inc. is identified as the operator, and the facility is operating. It is identified as part of Equinix Ashburn Campus. Spatial service-territory evidence associates the site with Dominion Virginia Power; the profile assigns the asset to PJM through that documented market role. Reported development, power, and commercial facts retain their source-specific facility, campus, building, or phase scope; the page does not collapse those values into a single implied load.
First phase opened in Q2 2020 with 1,600 cabinet equivalents and approx. 23,000 sq ft colocation space; total building 115,604 ft², 2‑story, precast‑concrete.
Also reported as DC15, Equinix DC15.
Equinix announces DC15 opened earlier in 2020 and that Equinix invested over $200M in Washington, D.C. area expansions including DC15; describes DC15 first phase cost (~$111M), initial cabinet capacity and mentions renewable energy procurement/CO2 footprint reduction in campus context.
Trade coverage noting Equinix opened DC15 earlier in the year and that DC21 opened later; repeats phase cost and initial capacity numbers for DC15 from corporate announcement.