Google Pumpkin Technology Campus
Under Construction
The Pumpkin Technology Campus is a data center campus along Interstate 20 and Appling Harlem Road in Harlem, Columbia County, Georgia. The original rezoning covered about 418 acres and a concept plan of four data center buildings, two warehouses and a substation. Google is identified as the project company, and blasting and extended-hours construction work were reported in October 2026. No megawatt figure for the campus has been published. Georgia Power is named as the utility that must confirm it can meet the campus power needs.