Las Vegas Data Center (LAS1)
Operating
Operating
DataBank’s LAS1 operates at 7185 Pollock Drive in Las Vegas as a colocation and interconnection facility. Its current page reports 3.35 MW of critical IT load and 57,364 IT square feet, with 2N power design and an N+1 cooling design. DataBank’s April 2024 acquisition announcement gave a different 3.55 MW figure; both are retained with their source dates rather than treated as utility-service capacity. NV Energy participates in the Western Energy Imbalance Market; that does not make LAS1 part of CAISO. NV Energy has announced planned Extended Day-Ahead Market participation for 2028.
DataBank announced the LAS1 expansion on March 9, 2022: add 10,000 sq ft of raised-floor space and 1.6 MW of power, with planned site totals of 30,000 sq ft of raised floor and 3 MW. A December 2022 DataBank tracker listed Q2 2022 availability; this is a forecast, not confirmation of actual operation. DataBank announced completion of expansions including Las Vegas on August 18, 2023. The exact LAS1 construction completion and actual online dates were not stated.
A 2014 report identifies a 2 MW NV Energy utility feed into the building; it does not identify the physical point of interconnection or its substation.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 3.35 MW | Critical IT Load | Reported | Exact Asset | — |
| DataBank’s current LAS1 page and datasheet report 3.35 MW of critical IT load. | ||||
| 3.55 MW | Critical IT Load | Reported | Exact Asset | 2024-04-01 |
| DataBank’s April 2024 acquisition announcement reported 3.55 MW of critical IT load; this differs from the current 3.35 MW figure and is retained as a separate dated report. | ||||
| 3 MW | Critical IT Load | Target | LAS1 expansion announced | — |
| The expansion announcement described a project intended to raise the site’s IT capacity to 3 MW of critical power. | ||||
| 1.4 MW | Critical IT Load | Reported | Exact Asset | — |
| The expansion announcement gave 1.4 MW as the site’s pre-expansion IT-capacity baseline. | ||||
| 2 MW | Utility Service | Reported | Exact Asset | — |
| A 2014 facility-upgrade report described a new 2 MW utility feed from NV Energy; this is a historical service figure, not a current contracted or energized capacity claim. | ||||
| 2 MW | Backup Generation | Reported | Exact Asset | — |
| A facility listing reports two generators rated at 2,000 kW each. The 2 MW value is per generator, not the combined rating. | ||||
Also reported as LAS1.
Covers DataBank's acquisition and identifies 7185 Pollock Drive as the location of LAS1.
Reports DataBank's acquisition of the facility it had leased, identifying it as LAS1 at 7185 Pollock Drive.
Reports DataBank's acquisition of its LAS1 edge data center at 7185 Pollock Drive.
DataBank's release announces its purchase of 7185 Pollock Drive, its LAS1 data center, and describes its stated service role in the Las Vegas area.
Reports DataBank's planned LAS1 expansion, identifying the 7185 Pollock Drive address and describing the proposed added space and capacity.
DataBank's press release announces the LAS1 expansion and describes its intended role in meeting regional customer demand.