Mesones Prime is a proposed data center campus on a tract in Jarrell, Williamson County, Texas, in the ERCOT region. The developer markets the land as a site prepared for AI and hyperscale compute and plans on-site natural gas generation alongside grid power. Utility, development and tax-incentive agreements had not been finalized in the latest dated report, and no end user has been named.
Loading map…
Overview
- Campus power
- 200 MW
- Available Power · Proposed
- Status
- Proposed
- Proposed campus
- Site
- 150.92 acres
- Campus
- Campus power
- 200 MW
- Parent campus · Onsite Generation
- Compute profile
- Hyperscale
- Project scope
- Campus at 3911 County Road 305, Jarrell, TX.
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 200 MW | Available Power | Proposed | Exact Asset | — |
| Available power at full buildout from natural gas and grid power | ||||
| 200 MW | Capacity basis unspecified | Proposed | Exact Asset | — |
| Developer's planned scalable site power | ||||
| About 264 MW | Capacity basis unspecified | Target | Exact Asset | — |
| Developer's expansion pathway beyond the planned site power | ||||
| 200 MW | Onsite Generation | Proposed | Campus | — |
| Dedicated power supply: Planned combined-cycle natural gas generation facility | ||||
- Utility
- Oncor
- ISO / RTO
Facility and development
- Site area (acres)
- 150.92
- Facility class
- Hyperscale
- Water source
- Municipal water and wastewater, per the developer
- Permits and dockets
- City council adopted annexation, land-use redesignation and rezoning ordinances on October 14
- Grid record
Organizations
Power Infrastructure PartnersDeveloperExact Asset
Prominent Property GroupDeveloperExact Asset