Meta Richland Parish Data Center
Under Construction
Under Construction
Meta’s Richland Parish Data Center is a major AI campus under construction near Rayville, Louisiana, within MISO. Entergy Louisiana’s service plan includes new high-voltage transmission, substations, combined-cycle generation, renewable resources, battery storage, and nuclear uprates. The campus is not yet operating, and later-phase dates remain development targets.
Original Richland Parish Data Center / Phase 1. Announced December 4, 2024 as a 4-million-square-foot campus with more than 2 GW of compute capacity. DPR identified four data-hall buildings plus a network building, with approximately 2 million square feet of data space within the 4-million-square-foot total build. Construction began in late 2024; the AI buildings began construction in 2025. Compute capacity is not treated as electrical MW.
Phase 2 of the Richland Parish campus. Turner states that Phase 2 will include ten data-center buildings totaling approximately 5.5 million square feet. Preconstruction is underway through June 2027, when building construction is scheduled to begin. The expanded campus is intended to support Hyperion and the announced 5 GW of compute capacity. No Phase 2-specific commercial-operation date or permit completion date is publicly stated; reports place full 5-GW delivery around 2032 and full physical build-out around 2036. Compute capacity is not treated as electrical MW.
Smalling Substation (Rayville Smalling); the initial plan also includes two Entergy-owned substations and six customer-owned substations.
Smalling Substation, which connects the Meta site to Entergy Louisiana's high-voltage transmission network.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 2,260 MW | Onsite Generation | Approved | Initial Meta Richland Parish service plan | 2025-08-20 |
| Combined capacity of three combined-cycle combustion turbines in the initial Meta Richland Parish service plan. Two facilities are located in Richland Parish and one is at Entergy's Waterford site, so 2,260 MW is not a site-only capacity figure. | ||||
Also reported as Hyperion Data Center, Meta Hyperion Campus, Richland Parish Data Center.
Covers the August 12, 2026 Louisiana Public Service Commission hearing and vote allowing Meta to keep confidential the information underlying its Hyperion job and electricity-use projections. It identifies the advocacy organizations seeking disclosure and the PSC's 3-1 vote to overturn the administrative judge's subpoena order.
Reports that the Richland Parish project was associated with more than $50 billion in investment, more than $1 billion in local infrastructure, projected construction and permanent jobs, and increased regional tax collections. The article also covers the PSC dispute over Meta's job and energy-use data.
Describes a Holly Ridge resident community meeting and a proposed monitoring effort focused on air, water, and dust near the Hyperion construction site. Residents raised questions about brown dust, diesel exhaust, water discoloration, power interruptions, roads, and health effects.
Reports that construction traffic around Meta's Hyperion site in Holly Ridge was associated with a reported increase of more than 600% in vehicle crashes, dangerous roads, and impacts near Holly Ridge Elementary School. Residents also described rust-colored water and unannounced power interruptions.
Describes the Smalling Substation, funded entirely by Meta, as infrastructure intended to connect Entergy's system to Meta's Richland Parish data center. The release reports construction employment and anticipated economic and customer benefits.
Lists the 12 2026 Meta Data Center Community Action Grant recipients in Richland Parish and describes their school, STEM, technology, and workforce-related projects.