Microsoft Elk Grove Village Data Center
Under Construction
Microsoft's Elk Grove Village data center is the first Microsoft building on its plot in the Elk Grove Technology Park, with a building permit application at 201 Innovation Dr. valued at $123 million. Microsoft paid Brennan Investment Group $52.2 million for the 36.6-acre parcel in January 2020, and grading and base work on the first building has been reported. The plot could eventually hold three data center buildings totaling 400,000 sq ft. Microsoft reportedly bought a parcel so ComEd could build a new substation in the park.
Loading map…
Overview
- Status
- Under Construction
- Under Construction
- Project cost
- $123.0M
- Estimated construction cost.
- Project scope
- Grading and base work for the first Microsoft building on the east side of Elk Grove Technology Park was reported under way; the 37-acre plot could eventually hold three data center buildings totaling 400,000 sq ft
- Power and grid
- Served by ComEd.
Power and grid
- Utility
- ComEd
- Market
- Nearest substations
- Unnamed substation138 kV
- Unnamed tap138 kV
Facility and development
- Construction
- Grading and base work for the first Microsoft building on the east side of Elk Grove Technology Park was reported under way; the 37-acre plot could eventually hold three data center buildings totaling 400,000 sq ft
- Land transaction
- Microsoft paid Brennan Investment Group $52.2 million for a 36.6-acre parcel on the east side of the Elk Grove Technology Park; the transaction closed in January 2020
- Project cost (USD)
- 123,000,000
- Permits and dockets