Microsoft Fairwater AI Datacenter — Mount Pleasant
Expanding
Expanding
Microsoft Fairwater is an operating and expanding AI data-center campus in Mount Pleasant, Wisconsin, within MISO and the We Energies service territory. Microsoft completed the first facility in June 2026 for large-scale AI training, while an adjacent second facility is under construction for planned completion in 2028 and another area remains in early site work. Public records distinguish the operating facility’s reported load from much larger campus interconnection figures, including a 1,480 MW large-load figure identified by MISO for 2026.
The initial southern project includes the MKE03 and MKE04 data center buildings and support infrastructure. Microsoft’s project materials state that site preparation began in June 2023 and that construction commenced in August 2023; foundation work began in November 2023. A December 2023 regional development bidding notice reported 337.6 MW for the MKE03/MKE04, administration-building, and central-utility-plant package. Microsoft announced that the first facility was completed and fully operational on June 23, 2026, after equipment was brought online and startup activities were conducted in April 2026.
Microsoft and Wisconsin officials announced on September 18, 2025, an additional approximately $4 billion investment for a second Mount Pleasant datacenter of similar size and scale. It is immediately adjacent to the first facility. Microsoft’s project update states that Phase 2 construction-related work began November 1, 2025, including foundation installation, steel erection, and underground utilities. The second facility is scheduled to be completed in 2028; no separate commercial-operation date has been stated.
The March 2026 project update identifies Phase 3 at Durand Avenue and Hewitt Memorial Drive, where preliminary earthwork was underway. Microsoft’s June 2026 presentation identifies the related Area 4/North parcel as an approved preliminary site plan in the earthwork phase; site clearing and geotechnical work were scheduled to continue through late 2027. No building count, floor area, capacity, construction-completion date, or commercial-operation date has been stated.
Mount Pleasant Substation. The broader Western Feed project also includes the planned Jupiter and Cosmos 345-kV substations, but the direct Fairwater point of interconnection is not separately identified in the public record.
Mount Pleasant Substation, through a 138-kV connection; a separate customer-side POI identifier was not publicly identified.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 58.75 MW | Utility Service | Operating | Exact Asset | — |
| Public facility listing reports 58.75 MW of power capacity for the operational Microsoft Mount Pleasant site. | ||||
| 35.25 MW | Critical IT Load | Operating | Exact Asset | — |
| Public facility listing reports 35.25 MW of IT load for the operational site; this is not treated as total campus power capacity. | ||||
| 450 MW | Interconnection Request | Reported | Phase 1 | — |
| Reported Phase 1 load figure in the Wisconsin regulatory record for Microsoft Mount Pleasant. | ||||
| 1,480 MW | Interconnection Request | Reported | Campus | — |
| MISO large-load announcement lists Microsoft Mount Pleasant, Wisconsin, at 1,480 MW for 2026. This is kept separate from the reported Phase 1 figure and the operational-site listing. | ||||
Also reported as Fairwater, Fairwater AI datacenter, Microsoft Mount Pleasant Data Centers, Mount Pleasant campus.
Mount Pleasant datacenter project update — Microsoft documented community office hours, a Community Connect open house, construction phases, construction-hour rules, and measures intended to reduce dust and roadway impacts.
Microsoft in Racine County – News & Updates — The regional economic-development organization reported Microsoft’s Mount Pleasant investment, projected employment, construction employment, workforce training, and campus phases.
WPR reported resident concerns about operational and construction noise, dust, light pollution, traffic, and landscape changes around Fairwater and its expansion areas.
The Wisconsin Examiner reported that three Sturtevant residents filed a proposed class action concerning noise from the Fairwater facility and sought to represent residents within 1.5 miles.
Microsoft described Fairwater as an AI datacenter in Mount Pleasant and outlined investment, workforce training, ecological restoration, broadband, and local-business commitments.
The DNR issued a site-specific public-hearing notice for Microsoft Mount Pleasant Data Centers at 4800 90th Street and identified the facility by FID 252302490.
Microsoft announced that the first Fairwater facility in Mount Pleasant was fully operational, reported nearly 550 on-site employees and nearly 10,000 construction workers, and described ongoing construction of an adjacent second facility.
The DNR published a second site-specific hearing notice concerning modifications to emergency generators, fire pumps, fuel usage, emission limits, and permit conditions.