Sabey Data Centers Ashburn - Building C
Operating
Operating
Sabey Data Centers Ashburn - Building C is a building data center in Ashburn, Loudoun, VA. Sabey Data Centers is identified as the operator, and the facility is operating. It is identified as part of Sabey Data Centers Ashburn. Spatial service-territory evidence associates the site with Dominion Virginia Power; the profile assigns the asset to PJM through that documented market role. Reported development, power, and commercial facts retain their source-specific facility, campus, building, or phase scope; the page does not collapse those values into a single implied load.
First phase (Building C) – 140,340 sq ft data center with 7.2 MW IT power and 2 MW generator capacity.
Second phase (Building B) – approx. 160,000 sq ft delivering 22 MW of mission‑critical power.
Third phase (Building A) – 125,000 sq ft facility slated for 2026 with 54 MW of leasable power.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 2 MW | Backup Generation | Reported | Building | — |
| 2 MW capacity generators with 72 hour run time at peak load | ||||
Campus Spotlight: Inside SDC Ashburn — Article spotlights SDC Ashburn campus, operated by Sabey Data Centers, and describes the upcoming third building slated for 2026 with 54 MW capacity.