Social Circle Technology Park Data Center Campus
Approved
Social Circle Technology Park, earlier filed as Newton County Technology Park, is a proposed nine-building data center campus north of I-20 near Social Circle, Georgia. Social Circle's city council rezoned the land to light industrial and unanimously approved a special-use permit in 2025. Georgia Power has reportedly committed to supply electricity through an on-site substation, but no megawatt load has been published, and no operator has been named.
Loading map…
Overview
- Campus power
- Not disclosed
- No exact-site MW figure in cited sources.
- Status
- Approved
- Approved campus
- IT floor area
- Not disclosed
- 9 reported buildings · Campus
- Build window
- 2031
- Applicant's regional review forecast for completion
- Project scope
- Applicant's regional review forecast for completion
- Power and grid
Power and grid
- Substation
- Two on-site substations proposed
Facility and development
- Buildings
- 9
- Water source
- Newton County Water and Sewerage Authority
- Permits and dockets
- Georgia Development of Regional Impact review DRI #4426, resubmitted from DRI #4376
- Grid record
- Two on-site substations proposed
- Regulatory record
Organizations
SC InfrastructureDeveloperExact Asset
TPA GroupDeveloperExact Asset