Stream Chicago II, also called ORDB, is the 226,000-square-foot data center at 1925 Busse Road in Elk Grove Village. Stream reports 32 MW of critical capacity at full build, a design figure rather than measured electricity demand. Development began in 2020 and phase-one commissioning started in the third quarter of 2022. The operator says the facility was fully leased in 2023 to unnamed cloud and hyperscale customers. Network distribution is redundant, and renewable power is offered as an option. This building is separate from Stream's Chicago I facility and developing Chicago III campus.
Loading map…
Overview
- Exact-site power
- 32 MW
- Critical IT Load · Reported
- Status
- Unknown
- Unknown building
- Facility size
- 226,000 sq ft
- 1 reported building · Building
- Compute profile
- Hyperscale
- Project scope
- Development began in 2020; phase-one commissioning started in Q3 2022. These milestones do not establish completion of all phases.
Power and grid
- Utility
- ComEd
- Market
- Nearest substations
- Unnamed substation138 kV
- Unnamed tap138 kV
Facility and development
- Gross floor area (sq ft)
- 226,000
- Buildings
- 1
- Construction
- Development began in 2020; phase-one commissioning started in Q3 2022. These milestones do not establish completion of all phases.
- Facility class
- Hyperscale