TeraWulf Justified Data Campus
Permitting
TeraWulf's Justified Data Campus is being developed at the former Century Aluminum Hawesville smelter, 1627 State Route 3543, Hawesville, Hancock County, Kentucky, in MISO. Anthropic signed a 20-year lease for about 401 MW of critical IT load, with initial capacity due in the second half of 2027 and the full 401 MW by early 2028. The campus has an energized on-site substation and is expected to join demand-response programs.
Loading map…
Overview
- Campus power
- 401 MW
- Critical IT Load · Contracted
- Status
- Permitting
- Permitting campus
- Site
- 790 acres
- Campus
- Build window
- 2H 2027 (initial); early 2028 (full 401 MW)
- Multi-phase build of about 401 MW critical IT for Anthropic on the former Century Aluminum Hawesville smelter site.
- Compute profile
- AI HPC
- Cooling design
Power and grid
- Utility
- Southern Indiana Gas & Elec Co
The site also falls inside the Kenergy Corp service territory.
- Market
- Substation
Energized on-site substation
- Nearest substations
- Unnamed substation161 kV
Facility and development
- Site area (acres)
- 790
- Facility class
- AI HPC
- Cooling systems
- Closed-loop cooling
- Regulatory record
- On August 21, 2026 the Kentucky PSC approved the RESA for up to 482 MW, finding it allocates risks appropriately and protects existing customers.
Timeline
- Anthropic lease phases announced.investors.t...