Vantage TX22 - San Antonio
Proposed
Proposed
Vantage Data Centers owns and will operate TX22, a proposed two-story, 214,526-square-foot hyperscale facility on 31 acres at 5207 Rogers Road, San Antonio, served by CPS Energy. TDLR registration is complete; construction is scheduled October 22, 2025 through June 15, 2027. The facility is designed to support cloud, AI/HPC, colocation, and enterprise workloads; no power capacity or commercial-operation date is established.
TX22 is a new two-story data center for data processing. TDLR lists it as privately funded on private land for private use, with a scheduled construction start of October 22, 2025 and scheduled completion of June 15, 2027. No expected commercial-online date, actual-online date, power capacity, data-hall area, or building count is explicitly reported for this exact facility.
Also reported as Vantage TX22, Vantage Data Centers TX22.
TPR reported the July 22 formal notice of intent to sue involving the Rogers Road and Omicron Drive projects, while expressly noting that the notice was a required pre-suit step and did not establish that the companies violated the law.
Local reporting described a July 22, 2026 notice of intent to sue concerning the Rogers Road and Omicron Drive campuses, identified the three environmental organizations involved, and reported the groups’ allegations regarding major-source permitting.
Local environmental reporting covered the May 28, 2026 TCEQ hearing for the TX2/TX21 permit associated with 5207 Rogers Road, including resident concerns about air quality, water, noise, construction impacts, and the relationship between the data center and on-site generation.
Local coverage identified Vantage’s newest facility as the 214,526-square-foot, two-story building at 5207 Rogers Road, near Creekside and Hidden Meadow, and reported the expected construction period and investment.
Trade coverage reported that Vantage filed for TX22, a second building at its San Antonio Rogers Road campus, and identified the exact address, size, construction schedule, estimated cost, and design firm.