Wildcat Point Generation Facility is a natural gas-fired power facility with 1,113.6 MW of EIA-reported nameplate capacity in Cecil County, Maryland, registered as EIA Plant ID 59220. Old Dominion Electric Coop is the registered plant entity or operator.
Mapped infrastructure geometry associated with this asset.
Natural Gas Fired Combined Cycle
Wildcat Point Generation Facility is currently operating; a closure or retirement is listed for August 2, 2026.
PJM
EIA plant 59220 · Inventory for Sep 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| CT1 | Natural Gas Fired Combined Cycle | Operating | 310.3 | Unknown |
| CT2 | Natural Gas Fired Combined Cycle | Operating | 310.3 | Unknown |
| ST1 | Natural Gas Fired Combined Cycle | Operating | 493 | Unknown |
Similar plants ranked by technology, capacity, and distance.
Current generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| CT1 | 310.3 MW 252.3 MW summer | Natural Gas Fired Combined Cycle CT | Apr 2018 | Operating |
| CT2 | 310.3 MW 241.1 MW summer | Natural Gas Fired Combined Cycle CT | Apr 2018 | Operating |
| ST1 | 493 MW 497.9 MW summer | Natural Gas Fired Combined Cycle CA | Apr 2018 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner.
PJM · Cecil County
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
| Largest reported plants | Capacity | State | |
|---|---|---|---|
| Wildcat Point Generation FacilityCurrent | 1,113.6 MW | MD | |
| Marsh Run Generation Facility | 596.7 MW | VA | |
| Louisa Generation Facility | 545.7 MW | VA | |
| Monterey Diesel Generation Facility | 6 MW | VA |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company.
EIA-860 lists generator CT1, generator CT2, generator ST1 with this operating date.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Wildcat Point Generation Facility reports 1,113.6 MW natural gas of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Sep 2026.
Wildcat Point Generation Facility is a Natural Gas Fired Combined Cycle facility in Cecil County, MD, participating in the PJM market.
Wildcat Point Generation Facility is in Cecil County, MD, inside the PJM balancing area.
Wildcat Point Generation Facility is operated by Old Dominion Electric Coop according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Wildcat Point Generation Facility reported 3,023.6 GWh over the twelve months to 2026-07. Figures are net generation as filed to EIA-923.
By capacity, Wildcat Point Generation Facility ranks #76 of 540 operating plants of the same technology nationally. It ranks #1 of 5 in MD.