PG&E Distribution Project Status

Where each PG&E distribution capacity project stands: overall status, any pause reason, and its original and current in-service dates.

Native record
event_time x object_id
weekly snapshot publication cadence
Evidence
Observed market data
Published observations from the named source
Time basis
Point-in-time records
UTC · event_time

Overview

Read one version at a time: `event_time = (SELECT max(event_time) FROM pge_grip.project_execution)`, with FINAL.

Query contract

Preserve one canonical row per (event_time, object_id) before aggregating.

Analysis rules

  • Group only after preserving the declared grain: event_time, object_id.

Access

Query from your own tools

Use the guarded HTTP endpoint directly, or connect an MCP client and load the dataset contract with describe_data before calling query_data.

HTTP endpoint
POST /api/v1/datasets/pge_grip_project_execution/query

Schema21

Column
Type
event_timeDateTime64(6, 'UTC')
observed_atNullable(DateTime64(6, 'UTC'))
object_idInt64
dupr_ddor_idNullable(String)
project_nameNullable(String)
project_typeLowCardinality(Nullable(String))
overall_statusLowCardinality(Nullable(String))
pause_reasonNullable(String)
order_numberNullable(String)
substation_idNullable(String)
gna_idsNullable(String)
gna_facility_idsNullable(String)
original_in_service_dateNullable(String)
current_in_service_dateNullable(String)
construction_start_dateNullable(String)
construction_end_dateNullable(String)
map_updated_textNullable(String)
attributes_jsonNullable(String)
longitudeNullable(Float64)
latitudeNullable(Float64)
ingested_atDateTime64(6, 'UTC')

Sample data

event_timeobserved_atobject_iddupr_ddor_idproject_nameproject_typeoverall_statuspause_reasonorder_numbersubstation_idgna_idsgna_facility_idsoriginal_in_service_datecurrent_in_service_dateconstruction_start_dateconstruction_end_datemap_updated_textattributes_jsonlongitudelatitudeingested_at
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938536098009Dinuba 1104 - Reconductor 1/0 and 4/0 with 715ALNew or upgraded circuitPlanned SolutionN/A3561593725409GNA_254091104_Capacity2540911042027-05-07 00:00:00∅∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": null, "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "254091104", "gna_id": "GNA_254091104_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 360, "order_no": "35615937", "original_expected_in_service_da": "2027-05-07 00:00:00", "overall_project_status": "Planned Solution", "planned_project_dupr_ddor_id_": "98009", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Dinuba 1104 - Reconductor 1/0 and 4/0 with 715AL", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25409", "year_need_first_identified": "2025", "year_planned_project_first_iden": "2025"}-119.39388736.5202282026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535998008CRESCENT SW STA-SCHINDLER - RPL PLNew or upgraded circuitOn-goingN/A3557585925289GNA_252891112_Capacity2528911122026-09-26 00:00:002026-05-26 00:00:002026-05-01 00:00:002026-05-26 00:00:0009/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-05-26 00:00:00", "date_project_is_initiated_": "2024-08-22 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "252891112", "gna_id": "GNA_252891112_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 359, "order_no": "35575859", "original_expected_in_service_da": "2026-09-26 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "98008", "project_construction_end_date_": "2026-05-26 00:00:00", "project_construction_start_date": "2026-05-01 00:00:00", "project_design_end_date_": "2024-10-16 00:00:00", "project_design_start_date_": "2024-09-12 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2024-08-23 00:00:00", "project_scoping_start_date_": "2024-08-23 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": "2025-10-09 00:00:00", "projecteasementsdesignpermittin": "2025-02-18 00:00:00", "projectname": "CRESCENT SW STA-SCHINDLER - RPL PL", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25289", "year_need_first_identified": "2024", "year_planned_project_first_iden": "2025"}-120.13844436.4019332026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535898006Cassidy- Border Coppermine 70kVNew or upgraded circuitCancelledN/A3556113025427GNA_254272107_Capacity2542721072025-02-07 00:00:00∅∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": null, "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "254272107", "gna_id": "GNA_254272107_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 358, "order_no": "35561130", "original_expected_in_service_da": "2025-02-07 00:00:00", "overall_project_status": "Cancelled", "planned_project_dupr_ddor_id_": "98006", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Cassidy- Border Coppermine 70kV", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25427", "year_need_first_identified": "2025", "year_planned_project_first_iden": "2025"}-119.81261136.9236922026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535753808RISING RIVER RECONDUCTOR 4300 FT (2026)New or upgraded circuitOn-goingN/A3565358910355GNA_1035501_None, GNA_103551101_Capacity1035501, 1035511012026-12-30 00:00:002026-10-01 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-10-01 00:00:00", "date_project_is_initiated_": "2025-08-15 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1035501, 103551101", "gna_id": "GNA_1035501_None, GNA_103551101_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 357, "order_no": "35653589", "original_expected_in_service_da": "2026-12-30 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "53808", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": "2026-05-06 00:00:00", "project_design_start_date_": "2025-10-02 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2025-10-03 00:00:00", "project_scoping_start_date_": "2025-10-03 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": "2026-06-16 00:00:00", "projecteasementsdesignpermittin": "2025-05-01 00:00:00", "projectname": "RISING RIVER RECONDUCTOR 4300 FT (2026)", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "10355", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.54329340.9286092026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535652842REPLACE LR 6502 - CLARKSVILLE 2109New or upgraded circuitPre-executionN/A3535499015361GNA_1536103_Capacity15361032026-12-16 00:00:002027-06-15 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-06-15 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1536103", "gna_id": "GNA_1536103_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 356, "order_no": "35354990", "original_expected_in_service_da": "2026-12-16 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "52842", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "REPLACE LR 6502 - CLARKSVILLE 2109", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "15361", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.05997938.6556482026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535552668NEW SUBSTATION_WEBER AREA - MARIPOSA RDSubstation UpgradesOn-goingN/A7406104416348GNA_1634804_None, GNA_1634805_Capacity1634804, 16348052029-02-13 00:00:002026-12-30 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-12-30 00:00:00", "date_project_is_initiated_": "2026-01-29 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1634804, 1634805", "gna_id": "GNA_1634804_None, GNA_1634805_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 355, "order_no": "74061044", "original_expected_in_service_da": "2029-02-13 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "52668", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "NEW SUBSTATION_WEBER AREA - MARIPOSA RD", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16348", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.24063837.9197782026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535451224WAHTOKE SUB - INSTALL 1102 FEEDERNew or upgraded circuitPre-executionN/A3569272025453GNA_254531108_Capacity, GNA_254531106_Capacity, GNA_254531107_Capacity, GNA_2545302_Capacity, GNA_2545303_None, GNA_2540901_Capacity, GNA_2522401_None254531108, 254531106, 254531107, 2545302, 2545303, 2540901, 25224012029-09-28 00:00:002029-09-30 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2029-09-30 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "254531108, 254531106, 254531107, 2545302, 2545303, 2540901, 2522401", "gna_id": "GNA_254531108_Capacity, GNA_254531106_Capacity, GNA_254531107_Capacity, GNA_2545302_Capacity, GNA_2545303_None, GNA_2540901_Capacity, GNA_2522401_None", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 354, "order_no": "35692720", "original_expected_in_service_da": "2029-09-28 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "51224", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "WAHTOKE SUB - INSTALL 1102 FEEDER", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25453", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-119.45225136.6152142026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535350832SUMMIT 1102 MAINLINE RECONDUCTORNew or upgraded circuitOn-goingN/A3505297815259GNA_1525901_N/A, GNA_152591102_Other1525901, 1525911022026-11-04 00:00:002026-11-17 00:00:002024-08-28 00:00:00∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-11-17 00:00:00", "date_project_is_initiated_": "2022-01-03 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1525901, 152591102", "gna_id": "GNA_1525901_N/A, GNA_152591102_Other", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 353, "order_no": "35052978", "original_expected_in_service_da": "2026-11-04 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "50832", "project_construction_end_date_": null, "project_construction_start_date": "2024-08-28 00:00:00", "project_design_end_date_": "2022-09-16 00:00:00", "project_design_start_date_": "2022-06-13 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2022-01-31 00:00:00", "project_scoping_start_date_": "2022-01-18 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": "2022-09-23 00:00:00", "projectname": "SUMMIT 1102 MAINLINE RECONDUCTOR", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "15259", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.37918439.3194552026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535254488Shady Glen - Replace BusSubstation UpgradesPre-executionN/A7407216015243GNA_1524301_Other15243012027-12-31 00:00:002027-05-10 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-05-10 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1524301", "gna_id": "GNA_1524301_Other", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 352, "order_no": "74072160", "original_expected_in_service_da": "2027-12-31 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "54488", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Shady Glen - Replace Bus ", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "15243", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.95381839.1152542026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535150067COALINGA #1: REPLACE BANK 2Substation UpgradesOn-goingN/A7406090225216GNA_2521602_Capacity25216022026-10-30 00:00:002026-04-24 00:00:002025-08-22 00:00:002025-10-30 00:00:0009/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-04-24 00:00:00", "date_project_is_initiated_": "2023-03-01 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "2521602", "gna_id": "GNA_2521602_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 351, "order_no": "74060902", "original_expected_in_service_da": "2026-10-30 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "50067", "project_construction_end_date_": "2025-10-30 00:00:00", "project_construction_start_date": "2025-08-22 00:00:00", "project_design_end_date_": "2025-03-25 00:00:00", "project_design_start_date_": "2023-03-28 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2024-04-30 00:00:00", "project_scoping_start_date_": "2023-03-28 00:00:00", "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": "2024-10-29 00:00:00", "projecteasementsdesignpermittin": null, "projectname": "COALINGA #1: REPLACE BANK 2", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25216", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.34415536.1362012026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938535048983PENRYN 1106 RECONDUCTORINGNew or upgraded circuitOn-goingN/A3567031215256GNA_1525602_Capacity, GNA_152561106_Capacity1525602, 1525611062027-12-30 00:00:002027-12-15 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-12-15 00:00:00", "date_project_is_initiated_": "2026-05-07 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1525602, 152561106", "gna_id": "GNA_1525602_Capacity, GNA_152561106_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 350, "order_no": "35670312", "original_expected_in_service_da": "2027-12-30 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "48983", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "PENRYN 1106 RECONDUCTORING", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "15256", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.16643238.8448612026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534947987SISQUOC 1102 - INSTALL 2 CAP BANKSSubstation UpgradesPre-executionN/A3543121618281GNA_1828102_None, GNA_182811102_Capacity1828102, 1828111022024-12-30 00:00:002028-12-31 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2028-12-31 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1828102, 182811102", "gna_id": "GNA_1828102_None, GNA_182811102_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 349, "order_no": "35431216", "original_expected_in_service_da": "2024-12-30 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "47987", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "SISQUOC 1102 - INSTALL 2 CAP BANKS", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "18281", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.33075634.8788862026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534846024Reconductor 397Al with 715Al on Olivehurst 1103New or upgraded circuitPre-executionN/A3573935115290GNA_152901103_Capacity, GNA_1520101_None, GNA_1529002_None, GNA_1520103_Capacity152901103, 1520101, 1529002, 1520103N/A2028-02-24 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2028-02-24 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "152901103, 1520101, 1529002, 1520103", "gna_id": "GNA_152901103_Capacity, GNA_1520101_None, GNA_1529002_None, GNA_1520103_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 348, "order_no": "35739351", "original_expected_in_service_da": "N/A", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "46024", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Reconductor 397Al with 715Al on Olivehurst 1103", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "15290", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.54283739.091912026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534745804RE-ROUTE FRENCH CAMP FEEDERSSubstation UpgradesPre-executionN/A7406986116329GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1632901_Capacity163291101, 163291104, 1632902, 16329012030-05-31 00:00:002030-06-01 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2030-06-01 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "163291101, 163291104, 1632902, 1632901", "gna_id": "GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1632901_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 347, "order_no": "74069861", "original_expected_in_service_da": "2030-05-31 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "45804", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "RE-ROUTE FRENCH CAMP FEEDERS", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16329", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.29042137.8818982026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534645804RE-ROUTE FRENCH CAMP FEEDERSNew or upgraded circuitOn-goingN/A3566121016329GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1632901_Capacity163291101, 163291104, 1632902, 16329012030-08-15 00:00:002026-05-05 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-05-05 00:00:00", "date_project_is_initiated_": "2026-02-19 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "163291101, 163291104, 1632902, 1632901", "gna_id": "GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1632901_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 346, "order_no": "35661210", "original_expected_in_service_da": "2030-08-15 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "45804", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "RE-ROUTE FRENCH CAMP FEEDERS", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16329", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.29042137.8818982026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534545265WEBER 1112 - PH2 - FEEDER EXTENSIONNew or upgraded circuitOn-goingN/A3571334516348GNA_163481111_Capacity, GNA_163291101_Capacity, GNA_163481113_Capacity, GNA_1634804_None, GNA_1634805_Capacity, GNA_1634806_Capacity, GNA_1632901_Capacity, GNA_1634803_None163481111, 163291101, 163481113, 1634804, 1634805, 1634806, 1632901, 16348032028-10-09 00:00:002027-01-09 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-01-09 00:00:00", "date_project_is_initiated_": "2026-02-03 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "163481111, 163291101, 163481113, 1634804, 1634805, 1634806, 1632901, 1634803", "gna_id": "GNA_163481111_Capacity, GNA_163291101_Capacity, GNA_163481113_Capacity, GNA_1634804_None, GNA_1634805_Capacity, GNA_1634806_Capacity, GNA_1632901_Capacity, GNA_1634803_None", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 345, "order_no": "35713345", "original_expected_in_service_da": "2028-10-09 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "45265", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": "2026-06-30 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2026-03-13 00:00:00", "project_scoping_start_date_": "2026-03-02 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "WEBER 1112 - PH2 - FEEDER EXTENSION", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16348", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.24063837.9197782026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534442769Stockton A 1106 Feeder Outlet ReplacementNew or upgraded circuitPre-executionN/A3573550016237GNA_162371106_Capacity, GNA_1623704_None162371106, 1623704N/A2027-12-16 16:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-12-16 16:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "162371106, 1623704", "gna_id": "GNA_162371106_Capacity, GNA_1623704_None", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 344, "order_no": "35735500", "original_expected_in_service_da": "N/A", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "42769", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Stockton A 1106 Feeder Outlet Replacement", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16237", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.28897137.9473112026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534342743Stockton A 1104 Feeder Outlet ReplacementNew or upgraded circuitPre-executionN/A3574194316237GNA_162371104_Capacity, GNA_1623703_Capacity162371104, 1623703N/A2027-12-16 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-12-16 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "162371104, 1623703", "gna_id": "GNA_162371104_Capacity, GNA_1623703_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 343, "order_no": "35741943", "original_expected_in_service_da": "N/A", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "42743", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Stockton A 1104 Feeder Outlet Replacement", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16237", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.28897137.9473112026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534242703ORO FINO 1102 - RECONDUCTOR TIER 3 HFTDNew or upgraded circuitOn-goingN/A3565429210303GNA_1030301_None, GNA_103031102_Capacity1030301, 1030311022026-06-29 00:00:002026-06-01 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-06-01 00:00:00", "date_project_is_initiated_": "2025-08-15 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1030301, 103031102", "gna_id": "GNA_1030301_None, GNA_103031102_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 342, "order_no": "35654292", "original_expected_in_service_da": "2026-06-29 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "42703", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": "2026-01-08 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2025-10-13 00:00:00", "project_scoping_start_date_": "2025-10-13 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": "2025-05-01 00:00:00", "projectname": "ORO FINO 1102 - RECONDUCTOR TIER 3 HFTD", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "10303", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.61103739.8716382026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534142283Stockton A Bank 5 UpgradeSubstation UpgradesPre-executionN/A7407326816348GNA_163481111_Capacity, GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1634806_Capacity, GNA_1623703_Capacity, GNA_1632901_Capacity, GNA_1623705_None, GNA_1623704_None163481111, 163291101, 163291104, 1632902, 1634806, 1623703, 1632901, 1623705, 16237042029-12-31 00:00:002028-01-08 16:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2028-01-08 16:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "163481111, 163291101, 163291104, 1632902, 1634806, 1623703, 1632901, 1623705, 1623704", "gna_id": "GNA_163481111_Capacity, GNA_163291101_Capacity, GNA_163291104_Capacity, GNA_1632902_Capacity, GNA_1634806_Capacity, GNA_1623703_Capacity, GNA_1632901_Capacity, GNA_1623705_None, GNA_1623704_None", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 341, "order_no": "74073268", "original_expected_in_service_da": "2029-12-31 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "42283", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "Stockton A Bank 5 Upgrade", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "16348", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-121.24063837.9197782026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938534042144KINGSBURG 1113 - RECONDUCTORING 6CNew or upgraded circuitPre-executionN/A3569417025224GNA_252241113_Capacity, GNA_2522403_None, GNA_252241113_Voltage252241113, 25224032026-07-13 00:00:002027-07-13 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-07-13 00:00:00", "date_project_is_initiated_": null, "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "252241113, 2522403", "gna_id": "GNA_252241113_Capacity, GNA_2522403_None, GNA_252241113_Voltage", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 340, "order_no": "35694170", "original_expected_in_service_da": "2026-07-13 00:00:00", "overall_project_status": "Pre-execution", "planned_project_dupr_ddor_id_": "42144", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": null, "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": null, "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "KINGSBURG 1113 - RECONDUCTORING 6C", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "25224", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-119.58249136.4886222026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938533938863SM1107 MAINLINE & RANCHITA CANYON RECONDNew or upgraded circuitOn-goingN/A3570738918266GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Capacity, GNA_182661107_Voltage1826601, 1826611072028-12-20 00:00:002027-01-12 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-01-12 00:00:00", "date_project_is_initiated_": "2025-09-11 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1826601, 182661107", "gna_id": "GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Capacity, GNA_182661107_Voltage", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 339, "order_no": "35707389", "original_expected_in_service_da": "2028-12-20 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "38863", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": "2025-12-10 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2026-06-01 00:00:00", "project_scoping_start_date_": "2025-12-09 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "SM1107 MAINLINE & RANCHITA CANYON RECOND", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "18266", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.68382135.7522252026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938533838863SM1107 MAINLINE & RANCHITA CANYON RECONDNew or upgraded circuitOn-goingN/A3570739018266GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Voltage1826601, 1826611072028-12-20 00:00:002027-01-23 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-01-23 00:00:00", "date_project_is_initiated_": "2025-09-11 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1826601, 182661107", "gna_id": "GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Voltage", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 338, "order_no": "35707390", "original_expected_in_service_da": "2028-12-20 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "38863", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": "2025-12-10 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2026-06-01 00:00:00", "project_scoping_start_date_": "2025-12-09 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "SM1107 MAINLINE & RANCHITA CANYON RECOND", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "18266", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.68382135.7522252026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.26938533738863SM1107 MAINLINE & RANCHITA CANYON RECONDNew or upgraded circuitOn-goingN/A3566321518266GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Capacity, GNA_182661107_Voltage1826601, 1826611072028-12-28 00:00:002027-01-12 00:00:00∅∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2027-01-12 00:00:00", "date_project_is_initiated_": "2025-09-11 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "1826601, 182661107", "gna_id": "GNA_1826601_Capacity, GNA_182661107_Reliability, GNA_182661107_Capacity, GNA_182661107_Voltage", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 337, "order_no": "35663215", "original_expected_in_service_da": "2028-12-28 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "38863", "project_construction_end_date_": null, "project_construction_start_date": null, "project_design_end_date_": null, "project_design_start_date_": "2025-12-10 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": "2026-06-01 00:00:00", "project_scoping_start_date_": "2025-12-09 00:00:00", "project_type": "New or upgraded circuit", "projecteasementsdesignpermitt_1": null, "projecteasementsdesignpermittin": null, "projectname": "SM1107 MAINLINE & RANCHITA CANYON RECOND", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "18266", "year_need_first_identified": "2026", "year_planned_project_first_iden": "2026"}-120.68382135.7522252026-09-25 20:50:02.721975
2026-09-11 16:51:24.2540002026-09-25 20:47:06.2693853363648306A - BORONDA 1102 FEEDER REINFORCMENTSubstation UpgradesOn-goingN/A7405384018296GNA_5243_Capacity1829611072028-10-04 00:00:002026-08-18 00:00:002026-03-09 00:00:00∅09/04/2026 19:40:32{"actual_peak_load_from_last_cycl": "N/A", "alternate_ddor_ids_if_applicabl": "N/A", "cost_of_completed_project_dolla": "N/A", "current_expected_or_actual_in_s": "2026-08-18 00:00:00", "date_project_is_initiated_": "2023-12-11 00:00:00", "description_of_workstreams_in_w": "N/A", "expense_account_for_completed_p": "N/A", "forecast_peak_load_from_last_cy": "N/A", "gna_facility_id_": "182961107", "gna_id": "GNA_5243_Capacity", "last_update_on_map": "09/04/2026 19:40:32", "objectid": 336, "order_no": "74053840", "original_expected_in_service_da": "2028-10-04 00:00:00", "overall_project_status": "On-going", "planned_project_dupr_ddor_id_": "36483", "project_construction_end_date_": null, "project_construction_start_date": "2026-03-09 00:00:00", "project_design_end_date_": null, "project_design_start_date_": "2024-04-08 00:00:00", "project_included_in_any_other_w": "No", "project_scoping_end_date_": null, "project_scoping_start_date_": "2024-04-08 00:00:00", "project_type": "Substation Upgrades", "projecteasementsdesignpermitt_1": "2025-07-03 00:00:00", "projecteasementsdesignpermittin": null, "projectname": "06A - BORONDA 1102 FEEDER REINFORCMENT", "publish": 1, "reason_for_project_pause_": "N/A", "substationid": "18296", "year_need_first_identified": "2025", "year_planned_project_first_iden": "2025"}-121.67105636.7848922026-09-25 20:50:02.721975

Coverage

100.0% complete0 gap days1 days with data
Show coverage history
Coverage: 100.0%Days with data: 1Gaps: 0