A natural-gas-fired combined-cycle power plant located at 50 Zorn Boulevard, Yaphank, Suffolk County, New York. The facility consists of two units with nameplate capacities of 196.2 MW and 152.7 MW, totaling 348.9 MW. Power output is primarily sold under a long-standing power purchase agreement with Long Island Power Authority. Lotus Infrastructure Partners, LP acquired 100% of the facility on January 7, 2026, and announced its intention to rename it Brookhaven Energy Center.

Overview

Key fields

Nameplate capacity
348.9 MW

Canonical EIA plant baseline.

Registry anchor
Plant 56234

plant-56234

Structured profile

Technology
Natural Gas Fired Combined Cycle
Operator
Caithness Long Island, LLC

Units and generators

Operating generator records and technology attributes reported through EIA-860.

GeneratorCapacityTechnologyOperationStatus
CT01196.2 MW
187.7 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CT
Aug 2009Operating
ST01152.7 MW
129.6 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CA
Aug 2009Operating

Performance

Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.

Peer context

Technology capacity
348.9 MW
Natural Gas Fired Combined Cycle
National rank
#339
of 538 operating peers
NY rank
#11
of 39 operating peers

Monthly generation

Download CSV
Latest 12 months
2.28 TWh
Reported net generation
Latest report
Apr 2026
EIA-923 monthly filing
2025 capacity factor
78.1%
Using current reported nameplate capacity
May 2023: 145 GWh2023-05Jun 2023: 206.7 GWhJul 2023: 214.8 GWhAug 2023: 218.4 GWhSep 2023: 211.3 GWhOct 2023: 153.8 GWhNov 2023: 224.5 GWh2023-11Dec 2023: 221.9 GWhJan 2024: 225.7 GWhFeb 2024: 213.5 GWhMar 2024: 216.9 GWhApr 2024: 35.2 GWhMay 2024: 0 MWh2024-05Jun 2024: 0 MWhJul 2024: 85.2 GWhAug 2024: 214.6 GWhSep 2024: 205.6 GWhOct 2024: 204.6 GWhNov 2024: 215.6 GWh2024-11Dec 2024: 236.7 GWhJan 2025: 243.2 GWhFeb 2025: 222.3 GWhMar 2025: 217.5 GWhApr 2025: 206 GWhMay 2025: 144.8 GWh2025-05Jun 2025: 208.2 GWhJul 2025: 181.1 GWhAug 2025: 172.7 GWhSep 2025: 198.1 GWhOct 2025: 146 GWhNov 2025: 216.7 GWh2025-11Dec 2025: 231.5 GWhJan 2026: 228.7 GWhFeb 2026: 189.6 GWhMar 2026: 160.3 GWhApr 2026: 204.5 GWh2026-04

Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.

Grid and market context

Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.

Nearby substations

HIFLD infrastructure inventory
IN SERVICE · 138 kV
0.6 km
IN SERVICE · 69 kV
2.2 km
IN SERVICE
2.3 km
IN SERVICE · 69 kV
2.3 km
IN SERVICE · 69 kV
2.3 km

Commercial, land, and environmental record

Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.

Transactions and agreements

Regulatory Filing
Jan 25, 2005
Caithness Long Island, LLC filed a petition for a Certificate of Public Convenience and Necessity (CPCN) to develop, own, and operate an approximately 346 megawatt electric generating plant in the Town of Brookhaven, Suffolk County.
Caithness Long Island, LLC · New York Public Service Commission
documents.dps.ny.gov
Acquisition Agreement
Sep 10, 2025
Lotus Infrastructure Partners and Caithness Energy announced a definitive agreement for Lotus to acquire 100% of the economic interests in Caithness Long Island Energy Center.
Lotus Infrastructure Partners, LP · Caithness Energy, LLC
lotusinfrastructure.com
Acquisition Closing
Jan 7, 2026
Lotus Infrastructure Partners, LP announced the closing of its acquisition of 100% of the economic interests in Caithness Long Island Energy Center from Caithness Energy, LLC. Following the closing, Lotus intends to rename the facility Brookhaven Energy Center.
Lotus Infrastructure Partners, LP · Caithness Energy, LLC
lotusinfrastructure.com

Related parties and identifiers

Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.

Relationship graph

Drag organizations to explore the network. Select a node to pin its details and available page link.

AssetOwner / operatorProject companyOfftaker

Parties and identifiers

RelationshipEntityBasis
Owner / O&M provider / asset managerLotus Infrastructure Partners, LPCurrent owner/acquirer per official closing announcement
Project company / owner / operatorCaithness Long Island, LLCProject company and former operator per PSC order and EIA listing
Former owner / developer / sponsorCaithness Energy, LLCDeveloper and seller per official transaction announcement
Offtaker / transmission owner / interconnecting utilityLong Island Power AuthorityTransmission/distribution owner and power purchaser per PSC order, EIA data, and NERC audit
Grid selectionplant:plant-56234Canonical asset page /nyiso/assets/plant/caithness-long-island-energy-center.

Reporting portfolio

EIA reporting entity
Caithness Long Island, LLC
Entity 49950
Operating portfolio
1 plants
1 states
Reported capacity
348.9 MW
Natural Gas Fired Combined Cycle

Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.

Timeline and sources

Project milestones and public references behind the asset profile.

Project timeline

  1. CPCN Petition Fileddocuments.d...

    Caithness Long Island, LLC filed a petition for a Certificate of Public Convenience and Necessity (CPCN) to develop, own, and operate an approximately 346 megawatt electric generating plant in the Town of Brookhaven, Suffolk County.

  2. Generators enter operationEIA-860

    EIA-860 lists generator CT01, generator ST01 with this operating date.

  3. Acquisition Agreement Announcedlotusinfras...

    Lotus Infrastructure Partners and Caithness Energy announced a definitive agreement for Lotus to acquire 100% of the economic interests in Caithness Long Island Energy Center.

  4. Acquisition closes; facility to be renamed Brookhaven Energy Centerlotusinfras...

    Lotus Infrastructure Partners, LP announced the closing of its acquisition of 100% of the economic interests in Caithness Long Island Energy Center from Caithness Energy, LLC. Following the closing, Lotus intends to rename the facility Brookhaven Energy Center.

Common questions about Caithness Long Island Energy Center

Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.

How big is Caithness Long Island Energy Center?

Caithness Long Island Energy Center has a reported capacity of 348.9 MW. Source: EIA Form 860M.

What kind of plant is Caithness Long Island Energy Center?

Caithness Long Island Energy Center is a Natural Gas Fired Combined Cycle facility in Suffolk County, NY, participating in the NYISO market.

Where is Caithness Long Island Energy Center located?

Caithness Long Island Energy Center is in Suffolk County, NY, inside the NYISO balancing area.

Who operates Caithness Long Island Energy Center?

Caithness Long Island Energy Center is operated by Caithness Long Island, LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.

How much electricity does Caithness Long Island Energy Center generate?

Caithness Long Island Energy Center reported 2,282 GWh over the twelve months to 2026-04. Figures are net generation as filed to EIA-923.

How does Caithness Long Island Energy Center compare to other plants?

By capacity, Caithness Long Island Energy Center ranks #339 of 538 operating plants of the same technology nationally. It ranks #11 of 39 in NY.

Asset analyst
plant:plant-56234

Ask about Caithness Long Island Energy Center

Investigate technology, capacity, output, price behavior, ownership, and related facilities using this profile plus current grid data.