Petroleum Liquids, Natural Gas Fired Combustion TurbineNYISO · Nassau Countyplant:plant-2679

Plant No 2 Freeport

Village of Freeport (New York) - Nassau County - NYISO

Operating electric utility power plant at 289 Buffalo Ave, Freeport, Nassau County, New York, consisting of an 18.1 MW petroleum-liquids combustion turbine that began operating in May 1973 and a 60.5 MW natural-gas-fired combustion turbine that began operating in April 2004, for a combined nameplate capacity of 78.6 MW. The 2004 project installed a GE LM6000 turbine and shared gas, electric-interconnection, substation, and site infrastructure with a separately owned merchant generator. The plant is municipally owned by the Village of Freeport and operates within NYISO Zone K.

Overview

Key fields

Nameplate capacity
78.6 MW

Canonical EIA plant baseline.

Registry anchor
Plant 2679

plant-2679

Structured profile

Technology
Petroleum Liquids, Natural Gas Fired Combustion Turbine
Operator
Freeport Electric

Units and generators

Operating generator records and technology attributes reported through EIA-860.

GeneratorCapacityTechnologyOperationStatus
318.1 MW
16.8 MW summer
Petroleum Liquids
Kerosene · GT
May 1973Operating
CT560.5 MW
49 MW summer
Natural Gas Fired Combustion Turbine
Natural Gas · GT
Apr 2004Operating

Performance

Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.

Peer context

Technology capacity
60.5 MW
Natural Gas Fired Combustion Turbine
National rank
#464
of 825 operating peers
NY rank
#13
of 31 operating peers

Monthly generation

Download CSV
Latest 12 months
31.1 GWh
Reported net generation
Latest report
Dec 2024
EIA-923 monthly filing
2024 capacity factor
4.5%
Using current reported nameplate capacity
Jan 2022: 7.4 GWh2022-01Feb 2022: 3.3 GWhMar 2022: 6.3 GWhApr 2022: 2.5 GWhMay 2022: 10.8 GWhJun 2022: 3.2 GWhJul 2022: 4.5 GWh2022-07Aug 2022: 8.6 GWhSep 2022: 2.4 GWhOct 2022: 273 MWhNov 2022: 3.1 GWhDec 2022: 3.3 GWhJan 2023: 712 MWh2023-01Feb 2023: 2.3 GWhMar 2023: 1.2 GWhApr 2023: 635 MWhMay 2023: 800 MWhJun 2023: 4.9 GWhJul 2023: 4.2 GWh2023-07Aug 2023: 771 MWhSep 2023: 2.8 GWhOct 2023: 958 MWhNov 2023: 4.2 GWhDec 2023: 1.1 GWhJan 2024: 2.2 GWh2024-01Feb 2024: 502 MWhMar 2024: 440 MWhApr 2024: 7 MWhMay 2024: 2.1 GWhJun 2024: 6.3 GWhJul 2024: 5.6 GWh2024-07Aug 2024: 4.4 GWhSep 2024: 1.7 GWhOct 2024: 1 GWhNov 2024: 1.3 GWhDec 2024: 5.4 GWh2024-12

Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.

Grid and market context

Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.

Nearby substations

HIFLD infrastructure inventory
IN SERVICE
0.1 km
IN SERVICE
2.7 km
IN SERVICE · 69 kV
2.7 km
IN SERVICE · 69 kV
2.8 km
IN SERVICE · 69 kV
3.6 km

Commercial, land, and environmental record

Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.

Related parties and identifiers

Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.

Relationship graph

Drag organizations to explore the network. Select a node to pin its details and available page link.

AssetOwner / operatorOrganizationContractorEquipment

Parties and identifiers

RelationshipEntityBasis
Operator / O&M providerFreeport ElectricOperator and manager of the municipal generation facility
Interconnection counterparty / transmission ownerLong Island Power Authority (LIPA)Transmission owner; electric-system interconnection partner
EPC contractor / construction contractorGFS, LLCPrimary contractor for construction of the 2004 generation facilities and ancillary equipment; comprised Greenman Pedersen Inc., Fresh Meadows Mechanical Corporation, and Peter Scalamandre & Sons, Inc.
EPC contractor / construction contractorWelsbach Electric CorporationContractor for construction of gas transmission line interconnection with KeySpan and electric transmission line interconnection with LIPA; worked in partnership with Bancker Construction
Equipment supplierGE VernovaManufacturer of the LM6000 aeroderivative gas turbine installed at Power Plant 2
DeveloperPPL GlobalSelected as preferred vendor by LIPA in February 2002 for the merchant-generator project at Power Plant 2; later withdrew from the project in 2003
DeveloperASH EnergySelected as LIPA's preferred developer to replace PPL Global for the separate merchant-generator project at Power Plant 2; negotiated site lease and development agreements with the Village
OwnerEquus Power I, L.P.Owner and operator of a separate 60 MW merchant generator colocated at 289 Buffalo Avenue, distinct from the Village-owned EIA plant 2679 units
Fuel supplier / interconnection counterpartyKeySpanNatural-gas transmission system interconnection partner; the 2.5-mile gas line from Power Plant 2 connects to the KeySpan transmission system
Grid selectionplant:plant-2679Canonical asset page /nyiso/assets/plant/plant-no-2-freeport.

Reporting portfolio

EIA reporting entity
Village of Freeport - (NY)
Entity 6775
Operating portfolio
2 plants
1 states
Reported capacity
84.6 MW
Natural Gas Fired Combustion Turbine · Petroleum Liquids
Largest reported plants in this portfolio
Largest reported plantsCapacityState
Plant No 2 FreeportCurrent78.6 MWNY
Plant No 1 Freeport6 MWNY

Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.

View full reporting portfolio

Timeline and sources

Project milestones and public references behind the asset profile.

Project timeline

  1. Generator enters operationEIA-860

    EIA-860 lists generator 3 with this operating date.

  2. New generation project advancedfreeportele...

    Freeport selected PPL Global as preferred vendor, arranged interim electricity supply with LIPA, and completed environmental review to advance the Power Plant 2 generation project

  3. Merchant Developer Changedfreeportele...

    LIPA selected ASH Energy as preferred developer for the second merchant generator after PPL Global withdrew from the project

  4. Generator enters operationEIA-860

    EIA-860 lists generator CT5 with this operating date.

  5. Municipal turbine entered operationfreeportele...

    The new municipal combustion turbine (CT5/LM6000) began operation on April 1, 2004. Integration with the new substation disconnected and effectively decommissioned old Power Plant 2 Units 1 and 2

Common questions about Plant No 2 Freeport

Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.

How big is Plant No 2 Freeport?

Plant No 2 Freeport has a reported capacity of 78.6 MW. Source: EIA Form 860M.

What kind of plant is Plant No 2 Freeport?

Plant No 2 Freeport is a Petroleum Liquids, Natural Gas Fired Combustion Turbine facility in Nassau County, NY, participating in the NYISO market.

Where is Plant No 2 Freeport located?

Plant No 2 Freeport is in Nassau County, NY, inside the NYISO balancing area.

Who operates Plant No 2 Freeport?

Plant No 2 Freeport is operated by Village of Freeport - (NY) according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.

How much electricity does Plant No 2 Freeport generate?

Plant No 2 Freeport reported 31.1 GWh over the twelve months to 2024-12. Figures are net generation as filed to EIA-923.

How does Plant No 2 Freeport compare to other plants?

By capacity, Plant No 2 Freeport ranks #464 of 825 operating plants of the same technology nationally. It ranks #13 of 31 in NY.

Asset analyst
plant:plant-2679

Ask about Plant No 2 Freeport

Investigate technology, capacity, output, price behavior, ownership, and related facilities using this profile plus current grid data.