Anadarko Plant
The Anadarko Plant in Caddo County, Oklahoma is a natural gas plant owned by Western Farmers Electric Cooperative. It runs five GE LM6000 PC gas turbines, two commissioned in 1999 and three in 2009. WFEC ordered two more LM6000VELOX aeroderivative units, named Roulet 12 and 13, to replace steam units that served for more than 60 years. Groundbreaking was held October 15, 2024, with completion targeted for late 2026 and Fagen as EPC contractor.