DataBank Red Oak Data Center Campus
Under Construction
Under Construction
The DataBank Red Oak campus is a data center development on Batchler Road in Red Oak, Ellis County, Texas. DataBank is building it on a 292-acre site, planned as eight two-story buildings. The first phase, four buildings leased to an AI company, is under construction, with a 400 MW Oncor substation on site. DataBank describes the full campus as 480 MW of critical IT power by a planned 2030 completion.
Four buildings, DFW9 through DFW12, fully leased to an AI company
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 480 MW | Critical IT Load | Proposed | Exact Asset | — |
| Full campus of eight buildings after the second phase, original announcement | ||||
| 480 MW | Critical IT Load | Target · target 2030 | Exact Asset | — |
| Planned completion of the full campus | ||||
| Up to 240 MW | Critical IT Load | Proposed | Exact Asset | — |
| First-phase design of four buildings in the original announcement | ||||
| Up to 300 MW | Critical IT Load | Reported | Exact Asset | — |
| Current campus page statement for the first phase; differs from the original 240 MW figure | ||||
| 400 MW | Utility Service | Proposed | Exact Asset | — |
| First-phase Oncor substation rating, not IT load | ||||
| Up to 800 MW | Utility Service | Proposed | Exact Asset | — |
| Substation expansion ceiling, not IT load | ||||
| 60 MW | Critical IT Load | Reported | Exact Asset | — |
| DFW9 design critical IT load | ||||
| 60 MW | Critical IT Load | Reported | Exact Asset | — |
| DFW10 design critical IT load | ||||
| 60 MW | Critical IT Load | Reported | Exact Asset | — |
| DFW11 design critical IT load | ||||
| 60 MW | Critical IT Load | Reported | Exact Asset | — |
| DFW12 design critical IT load | ||||
| 180 MW | Capacity basis unspecified | Under Construction | Exact Asset | — |
| First three leased buildings, basis not specified | ||||