Fagus Solar Park
Excel Advantage Services, LLC - Childress County - ERCOT
Fagus Solar Park, also known as Misae Solar Park II, Misae Solar II, Misae II, and Misae Solar Park II, is a 331.6 MWac ground-mounted solar photovoltaic facility in Childress County, Texas. The project is owned and operated by Excel Advantage Services, LLC, a U.S. subsidiary of Spanish renewable-energy producer Greenalia, which acquired the Misae II project in July 2021. The facility is located on approximately 2,471 acres (1,000 hectares) of leased land and features 1,760,640 Jinko Solar 395 W monocrystalline modules, 620 TMEIC 840 kVA inverters, and 1,838 Grupo Clavijo single-axis trackers. The plant connects to the ERCOT grid via a 345 kV transmission line (Tesla-to-Fagus) and serves as a transmission-grade resource interconnected at the Fagus Substation. The project was engineered with a nameplate capacity of approximately 517.35 MW DC, stepped down to 331.6 MW AC after inversion. Annual energy generation is estimated at approximately 865 GWh.