Guajillo Energy Storage is a 200 MW / 400 MWh lithium iron phosphate battery in Webb County, Texas, about 20 km from Laredo, owned by Plenitude through Eni New Energy US. BayWa r.e. developed it and sold it to Eni New Energy US in February 2022 alongside the Corazon I solar plant, whose interconnection it shares at the Corazon Solar 345-kV substation on Electric Transmission Texas's system.
Mapped infrastructure geometry associated with this asset.
EIA plant 68613 · Inventory for Sep 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| GUAJ1 | Batteries | Operating | 228.7 | 228.7 |
Mapped infrastructure geometry associated with this asset.
Similar plants ranked by technology, capacity, and distance.
Current generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| GUAJ1 | 228.7 MW 200 MW summer | Batteries BA | Dec 2025 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Where the plant sits in ERCOT: its market, pricing node, utility territory and the network around it, each with how it is known.
The site also falls inside the Rio Grande Electric Coop, Inc service territory.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
Acquired at advanced development with the Corazon I solar plant; target operation before end-2023.
EIA-923 reports gross generation and net grid exchange for storage plants. Gross generation is shown as a discharge proxy; it is not a cycle count or conventional capacity factor.
1 ERCOT market resource · Battery / storage
Cycles/day is discharged energy vs. usable capacity (~254 MWh). Capacity factor is avg discharge vs. peak.
Observed ERCOT settlement prices at CORAZON_RN over 365 days (2025-11-10 to 2026-11-09).
The TB2 figure is a price benchmark, not revenue: it values one perfect-foresight cycle per day between the 2 cheapest and 2 dearest hours of each day, gross of round-trip losses, and excludes ancillary services. It describes what this node’s price shape was worth over the window — it is not this asset’s realized capture, and no dispatch is assumed or modelled.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Plenitude announced construction complete; commercial operation scheduled by mid-2025.
EIA-860 lists generator GUAJ1 with this operating date.
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Guajillo Energy Storage reports 228.7 MW battery storage of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Sep 2026.
Guajillo Energy Storage is a batteries facility in Webb County, TX, participating in the ERCOT market.
Guajillo Energy Storage is in Webb County, TX, inside the ERCOT balancing area.
Guajillo Energy Storage is operated by Guajillo Energy Storage, LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Guajillo Energy Storage reported 50.1 GWh over the twelve months to 2026-08. For a storage plant this is reported gross generation — a discharge proxy, not a cycle count or a conventional capacity factor.
By capacity, Guajillo Energy Storage ranks #48 of 1,061 operating plants of the same technology nationally. It ranks #14 of 254 in TX.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.