Heartland Divide II
Heartland Divide II is the 200 MW second phase of NextEra Energy's Heartland Divide Wind Energy project in Audubon County, Iowa. The facility consists of 66 GE 2.82 MW and 6 GE 2.32 MW wind turbines tied together by a 34.5 kV underground collection system. Construction began in mid-2021, following a first phase of about 100 MW completed in 2019.
Overview
- Registry anchor
- Plant 64661
- plant-64661
Infrastructure record
- Alternate name
- Heartland Divide II Wind
- Turbines
- 11
- Manufacturers