Microsoft Lambda Drive Datacenter Campus
Operating · Microsoft · 15434 Lambda Dr, San Antonio, TX
Microsoft's Lambda Drive datacenter campus is in the Texas Research Park on San Antonio's far West Side, in Bexar County. Microsoft bought 158 acres there in December 2015. Texas TDLR filings list SAT46, a 79,385 sq ft data center building on the existing campus (2021–2022), and SAT40, a 153,227 sq ft data center at 15000 Lambda Drive with an estimated cost of $175.9 million. Bexar Appraisal District figures cited by local press put Microsoft's Lambda Drive data centers at 850,000 sq ft built since 2016. Turner Construction is the general contractor.
Overview
- Campus power
- Not disclosed
- No exact-site MW figure in cited sources.
- Status
- Operating
- Operating campus
- IT floor area
- Not disclosed
- Campus
- Campus buildout
- 153,227 sq ft
- SAT40 · Reported
- Project scope
- Microsoft has built about 850,000 sq ft of data centers on Lambda Drive since 2016; SAT40, a $175.9 million building on 70 acres, was built by Turner Construction.
Power and grid
Facility and development
- Construction
- Microsoft has built about 850,000 sq ft of data centers on Lambda Drive since 2016; SAT40, a $175.9 million building on 70 acres, was built by Turner Construction.
- Land transaction
- Microsoft bought 158 acres in the Texas Research Park in December 2015 for a planned $1 billion data center development.
- Permits and dockets
- Texas TDLR TABS2021012189 (SAT46) · Texas TDLR TABS2023013247 (SAT40)
- Grid record