Peregrine Energy Storage is Arevon’s 200 MW / 400 MWh battery in San Diego’s Barrio Logan neighborhood. Arevon announced the project fully operational in June 2025. Its underground connection reaches SDG&E’s Silvergate Substation. The power and energy ratings correspond to two hours of storage at rated output.
Mapped infrastructure geometry associated with this asset.
Illustrative BESS equipment layout for comparing sites. Not an as-built site map.
EIA plant 66286 · Inventory for Oct 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| PERE1 | Batteries | Operating | 200 | 400 |
Mapped infrastructure geometry associated with this asset.
Arevon identifies itself as Peregrine’s developer and owner. The documented SDG&E relationship is the grid connection to Silvergate Substation.
Source: Arevon Peregrine operational announcement · as of 2025-07-30
Arevon reports 200 MW of power and 400 MWh of stored energy. Dividing energy by rated power gives two hours; actual dispatch depends on the battery’s operating conditions and available charge.
Source: Arevon Peregrine operational announcement · as of 2025-07-30
The project’s June 2025 fact sheet identifies SDG&E Silvergate Substation as the point of interconnection and describes the transmission facilities as underground.
Source: Peregrine June 2025 project fact sheet · as of 2025-06
Similar plants ranked by technology, capacity, and distance.
Current generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| PERE1 | 200 MW 200 MW summer | Batteries BA | Jun 2025 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Where the plant sits in CAISO: its market, pricing node, utility territory and the network around it, each with how it is known.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Project milestones and public references behind the asset profile.
EIA-923 reports gross generation and net grid exchange for storage plants. Gross generation is shown as a discharge proxy; it is not a cycle count or conventional capacity factor.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
EIA-860 lists generator PERE1 with this operating date.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Arevon identifies itself as Peregrine’s developer and owner. The documented SDG&E relationship is the grid connection to Silvergate Substation.
Arevon reports 200 MW of power and 400 MWh of stored energy. Dividing energy by rated power gives two hours; actual dispatch depends on the battery’s operating conditions and available charge.
The project’s June 2025 fact sheet identifies SDG&E Silvergate Substation as the point of interconnection and describes the transmission facilities as underground.
Peregrine Energy Storage reports 200 MW battery storage of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Oct 2026.
Peregrine Energy Storage is a Lithium-iron-phosphate battery storage facility in San Diego County, CA, participating in the CAISO market.
Peregrine Energy Storage is in San Diego County, CA, inside the CAISO balancing area.
Peregrine Energy Storage is operated by Peregrine Energy Storage, LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Peregrine Energy Storage reported 140.8 GWh over the twelve months to 2026-08. For a storage plant this is reported gross generation — a discharge proxy, not a cycle count or a conventional capacity factor.
Peregrine Energy Storage interconnects at Silvergate.
By capacity, Peregrine Energy Storage ranks #58 of 1,061 operating plants of the same technology nationally. It ranks #15 of 272 in CA.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.