STACK Infrastructure SVY01
Expanding · 2001 Fortune Drive, San Jose, CA
STACK SVY01 is a four-building data center campus on 19 acres at 2001 Fortune Drive in San Jose, California. STACK is working with PG&E on new power infrastructure.
Overview
- Campus power
- 60 MW
- Capacity basis unspecified · Reported
- Status
- Expanding
- Expanding campus
- Site
- 19 acres
- 4 reported buildings · Campus
- Campus buildout
- 240,000 sq ft
- SVY01B · Reported
- Project scope
- Expansion of two data centers, an advanced manufacturing facility and a parking structure, announced with a groundbreaking in March 2024.
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 60 MW | Capacity basis unspecified | Reported | Expansion | — |
| Operator-reported capacity of the 2024 expansion, basis unspecified. | ||||
Facility and development
- Site area (acres)
- 19
- Buildings
- 4
- Construction
- Expansion of two data centers, an advanced manufacturing facility and a parking structure, announced with a groundbreaking in March 2024.
- Utility agreements
- PG&E Direct Access program serves the campus, enabling STACK to procure energy from renewable sources on behalf of clients