Highgate

ISO-NE ↔ Hydro-Québec · Back-to-back HVDC converter

A back-to-back HVDC converter at Highgate, Vermont, bringing Québec power into northern Vermont.

Now
0 MWIdle
ISO-NE · as of Nov 10, 6:35 PM EST
Loading map…

Operator readings

Compare each operator’s reading at its stated time. Scheduled transfers and metered physical flow measure different things.

As ISO-NE reports it
0 MW · Idle

Current reading · as of Nov 10, 6:35 PM EST

Last 30 days

Hourly readings, signed so that up is power leaving the market. Each series identifies whether it measures flow or a transfer schedule.

-300-200-1000Latest readingOct 15Oct 22Oct 29Nov 5

Above zero: ISO-NE → Hydro-Québec. Below: the reverse.

Usual direction
Hydro-Québec → ISO-NE in 25% of hours

0% out, 25% in, 75% idle across 720 hours

Average
17 MW · Hydro-Québec → ISO-NE
When busy
98 MW

95th percentile of hourly flow either way

Peak ISO-NE → Hydro-Québec
0 MW
Peak Hydro-Québec → ISO-NE
210 MW
Direction changes
0
Hours near its rating
0 of 720

At 95% or more of 225 MW

The average day
0:006:0012:0018:0023:00
Mean reading by the market's local hour. Up: ISO-NE → Hydro-Québec. Down: Hydro-Québec → ISO-NE.

Hardware

Its terminals, placed from named HIFLD substations or other cited geospatial sources where available.

Substation
Bedford, Québec

In Canada, outside HIFLD's coverage

Converter
Highgate converter, VT

44.9404, -73.0515 · 115 kV

Sources and method

Readings come from ISO-NE interface readings. Each value is shown with its operator and source time; direction is normalized from that operator’s sign convention toward or away from ISO-NE. A rating describes the equipment; an operator’s posted directional limit, when available, is a separate operating value. The map point identifies a sourced terminal or crossing where available, or a representative connection point; it does not trace the full route.