MISO logo

MISO–Manitoba Hydro

MISO ↔ Manitoba Hydro · Market seam (every AC tie between two markets)

The ties between Manitoba Hydro and MISO across the Minnesota and North Dakota border, carrying Manitoba hydro south.

Last reported · update overdue
1,040 MWManitoba Hydro → MISO
MISO · as of Nov 9, 10:00 PM CST
Loading map…

Operator readings

Compare each operator’s reading at its stated time. Scheduled transfers and metered physical flow measure different things.

As MISO reports it
1,040 MW · Manitoba Hydro → MISO

Update overdue · as of Nov 9, 10:00 PM CST

Last 30 days

Hourly readings, signed so that up is power leaving the market. Each series identifies whether it measures flow or a transfer schedule.

-2,000-1,00001,000Latest readingOct 15Oct 22Oct 29Nov 5

Above zero: MISO → Manitoba Hydro. Below: the reverse.

Usual direction
Manitoba Hydro → MISO in 98% of hours

2% out, 98% in, 0% idle across 581 hours

Average
1,022 MW · Manitoba Hydro → MISO
When busy
1,673 MW

95th percentile of hourly flow either way

Peak MISO → Manitoba Hydro
366 MW
Peak Manitoba Hydro → MISO
1,931 MW
Direction changes
4
The average day
0:006:0012:0018:0023:00
Mean reading by the market's local hour. Up: MISO → Manitoba Hydro. Down: Manitoba Hydro → MISO.

Sources and method

Readings come from MISO interface readings. Each value is shown with its operator and source time; direction is normalized from that operator’s sign convention toward or away from MISO. A rating describes the equipment; an operator’s posted directional limit, when available, is a separate operating value. The map point identifies a sourced terminal or crossing where available, or a representative connection point; it does not trace the full route.