| 1 | 2026-11-23 21:40:06.367706 | 2026-11-23 21:40:06.367706 | 2026 | fish_passage_changes | https://public.crohms.org/tmt/documents/fpp/2026/changes/ | b4962b4328de6becc2aca055edeabc3e5edf8608f1c3569ccd308fbfc5892f6a | 0 | 0 | DRAFT 2026 FPP
Draft 2026 Fish Passage Plan (FPP)
& Change Forms
* Change Forms FINALIZED after March 1, 2026, are NOT included in the print version of the 2026 FPP.
Draft
Chapters & Appendices
Change
Forms
Date
Posted
Change Form
Status
Draft Chapter 1 - Overview
Draft Chapter 2 - Bonneville Dam
26BON001 - PH2 Unit Operating Range
2-FEB-2026
PENDING
26BON002 - PH1 115kV Support
11-FEB-2026
FINALIZED
26BON003 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 3 - The Dalles Dam
26TDA001 - PUD Juvenile Monitoring
2-FEB-2026
FINALIZED
26TDA002 - List of Species
2-FEB-2026
FINALIZED
26TDA003 - E2, E3
2-FEB-2026
FINALIZED
26TDA004 - Turbine Maintenance
2-FEB-2026
FINALIZED
26TDA005 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 4 - John Day Dam
26JDA001 - Clarify Unit Priority
2-FEB-2026
FINALIZED
26JDA002 - Unit 7 Fixed-Blades
2-FEB-2026
FINALIZED
26JDA003 - Table JDA-8 Title
2-FEB-2026
WITHDRAWN
26JDA004 - Corrected Forebay Ranges
12-FEB-2026
FINALIZED
26JDA005 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 5 - McNary Dam
26MCN001 - Unit Priority for 2026
2-FEB-2026
FINALIZED
26MCN002 - Court Order Updates
25-MAR-2026
FINALIZED
26MCN003 - Double-Leaf Gates Criteria
1-APR-2026
FINALIZED
26MCN004 - Low Flow Spill Patterns
11-JUN-2026
FINALIZED
26MCN005 - Criteria to Close Double-Leaf Gates
11-JUN-2026
FINALIZED
Draft Chapter 6 - Ice Harbor Dam
26IHR001 -Staff Gauges
2-FEB-2026
FINALIZED
Draft Chapter 7 - Lower Monumental Dam
26LMN001 - Forebay Trash Rack Criteria
12-MAR-2026
FINALIZED
26LMN002 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 8 - Little Goose Dam
26LGS001 - Channel Lighting
2-FEB-2026
FINALIZED
26LGS002 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 9 - Lower Granite Dam
26LWG001 - Low Flow Spill Patterns
2-FEB-2026
FINALIZED
26LWG002 - Adult Fish Facilities Verbiage
3-FEB-2026
FINALIZED
26LWG003 - ESBS/VBS Inspections
3-FEB-2026
WITHDRAWN
26LWG004 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Appendix A - Special Ops & Studies
26AppA001 - Doble Testing Schedule
3-FEB-2026
FINALIZED
Draft Appendix B - Transport Plan
26AppB001 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Appendix C - BPA Load Shaping Guidelines
Draft Appendix D - Ops for Lamprey
26AppD001 - TDA Updates
3-FEB-2026
FINALIZED
26AppD002 - BON Lamprey Updates
3-FEB-2026
FINALIZED
Draft Appendix E - Fish Operations Plan (FOP)
N/A (coordinated via RIOG)
------
------
Draft Appendix F - Dewatering Fish Salvage
Draft Appendix G - Adult Trap Ops
Draft Appendix H - CHJ Turbine Dewatering
Draft Appendix I - DWR Turbine Maintenance
Draft Appendix J - Smolt Facility Protocols
26AppJ001 - JDA Updates
3-FEB-2026
FINALIZED
26AppJ002 - Task Group Updates
25-MAR-2026
FINALIZED
Draft Appendix K - Acronyms
Draft Appendix L - Predator Mgmt Plans
26AppL001 - 2026 Updates
3-FEB-2026
FINALIZED
Draft Appendix M - Albeni Falls Fish Protection Procedures
26AppM001 - AFD Dewatering Procedures
3-FEB-2026
FINALIZED
Fish Passage Plan Homepage | 2026-11-23 21:40:06.447238 |
| 2 | 2026-11-20 21:40:12.569609 | 2026-11-20 21:40:12.569609 | 2026 | fish_passage_changes | https://public.crohms.org/tmt/documents/fpp/index.html | b2e1a366fc939d3f1043be9a9c946310c1af53cf7b574c90ce645ea82be8024a | 0 | 0 | FPP Homepage
Fish Passage Plan (FPP) Homepage
* In effect through February 2027
2027
Change Forms
2026
FINAL
*
Change Forms
2025
FINAL
Change Forms
2024
FINAL
Change Forms
2023
FINAL
Change Forms
2022
FINAL
Change Forms
2021
FINAL
Change Forms
2020
FINAL
Change Forms
2019
FINAL
Change Forms
2018
FINAL
Change Forms
2017
FINAL
Change Forms
2016
FINAL
Change Forms
2015
FINAL
Change Forms
2014
FINAL
Change Forms
2013
FINAL
Change Forms
2012
FINAL
Change Forms
2011
FINAL
Change Forms
2010
FINAL
Change Forms
2009
FINAL
2008
FINAL
2007
FINAL
2006
FINAL
2005
FINAL
2004
FINAL
2003
FINAL
2002
FINAL
2001
FINAL
2000
FINAL
1996
FINAL | 2026-11-20 21:40:12.598274 |
| 3 | 2026-11-20 21:40:08.525535 | 2026-11-20 21:40:08.525535 | 2026 | fish_passage_changes | https://public.crohms.org/tmt/documents/fpp/2026/changes/ | a312bacf11386f96f599ae1f23372f4348ad327d026b95db696e1d60d5d86323 | 0 | 0 | DRAFT 2026 FPP
Draft 2026 Fish Passage Plan (FPP)
& Change Forms
* Change Forms FINALIZED after March 1, 2026, are NOT included in the print version of the 2026 FPP.
Draft
Chapters & Appendices
Change
Forms
Date
Posted
Change Form
Status
Draft Chapter 1 - Overview
Draft Chapter 2 - Bonneville Dam
26BON001 - PH2 Unit Operating Range
2-FEB-2026
PENDING
26BON002 - PH1 115kV Support
11-FEB-2026
FINALIZED
26BON003 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 3 - The Dalles Dam
26TDA001 - PUD Juvenile Monitoring
2-FEB-2026
FINALIZED
26TDA002 - List of Species
2-FEB-2026
FINALIZED
26TDA003 - E2, E3
2-FEB-2026
FINALIZED
26TDA004 - Turbine Maintenance
2-FEB-2026
FINALIZED
26TDA005 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 4 - John Day Dam
26JDA001 - Clarify Unit Priority
2-FEB-2026
FINALIZED
26JDA002 - Unit 7 Fixed-Blades
2-FEB-2026
FINALIZED
26JDA003 - Table JDA-8 Title
2-FEB-2026
WITHDRAWN
26JDA004 - Corrected Forebay Ranges
12-FEB-2026
FINALIZED
26JDA005 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 5 - McNary Dam
26MCN001 - Unit Priority for 2026
2-FEB-2026
FINALIZED
26MCN002 - Court Order Updates
25-MAR-2026
FINALIZED
26MCN003 - Double-Leaf Gates Criteria
1-APR-2026
FINALIZED
26MCN004 - Low Flow Spill Patterns
11-JUN-2026
FINALIZED
26MCN005 - Criteria to Close Double-Leaf Gates
11-JUN-2026
FINALIZED
Draft Chapter 6 - Ice Harbor Dam
26IHR001 -Staff Gauges
2-FEB-2026
FINALIZED
Draft Chapter 7 - Lower Monumental Dam
26LMN001 - Forebay Trash Rack Criteria
12-MAR-2026
FINALIZED
26LMN002 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 8 - Little Goose Dam
26LGS001 - Channel Lighting
2-FEB-2026
FINALIZED
26LGS002 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Chapter 9 - Lower Granite Dam
26LWG001 - Low Flow Spill Patterns
2-FEB-2026
FINALIZED
26LWG002 - Adult Fish Facilities Verbiage
3-FEB-2026
FINALIZED
26LWG003 - ESBS/VBS Inspections
3-FEB-2026
WITHDRAWN
26LWG004 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Appendix A - Special Ops & Studies
26AppA001 - Doble Testing Schedule
3-FEB-2026
FINALIZED
Draft Appendix B - Transport Plan
26AppB001 - Court Order Updates
25-MAR-2026
FINALIZED
Draft Appendix C - BPA Load Shaping Guidelines
Draft Appendix D - Ops for Lamprey
26AppD001 - TDA Updates
3-FEB-2026
FINALIZED
26AppD002 - BON Lamprey Updates
3-FEB-2026
FINALIZED
Draft Appendix E - Fish Operations Plan (FOP)
N/A (coordinated via RIOG)
------
------
Draft Appendix F - Dewatering Fish Salvage
Draft Appendix G - Adult Trap Ops
Draft Appendix H - CHJ Turbine Dewatering
Draft Appendix I - DWR Turbine Maintenance
Draft Appendix J - Smolt Facility Protocols
26AppJ001 - JDA Updates
3-FEB-2026
FINALIZED
26AppJ002 - Task Group Updates
25-MAR-2026
FINALIZED
Draft Appendix K - Acronyms
Draft Appendix L - Predator Mgmt Plans
26AppL001 - 2026 Updates
3-FEB-2026
FINALIZED
Draft Appendix M - Albeni Falls Fish Protection Procedures
26AppM001 - AFD Dewatering Procedures
3-FEB-2026
FINALIZED
Fish Passage Plan Homepage | 2026-11-20 21:40:08.627554 |
| 4 | 2026-11-16 21:40:12.884003 | 2026-11-16 21:40:12.884003 | 2026 | fish_passage_changes | https://public.crohms.org/tmt/documents/fpp/index.html | 4784d542c46a01c517991c987c4b2f9eaed9688fe9293aedf4da02ff7b6229c3 | 0 | 0 | FPP Homepage
Fish Passage Plan (FPP) Homepage
* In effect through February 2027
2026
FINAL
*
Change Forms
2025
FINAL
Change Forms
2024
FINAL
Change Forms
2023
FINAL
Change Forms
2022
FINAL
Change Forms
2021
FINAL
Change Forms
2020
FINAL
Change Forms
2019
FINAL
Change Forms
2018
FINAL
Change Forms
2017
FINAL
Change Forms
2016
FINAL
Change Forms
2015
FINAL
Change Forms
2014
FINAL
Change Forms
2013
FINAL
Change Forms
2012
FINAL
Change Forms
2011
FINAL
Change Forms
2010
FINAL
Change Forms
2009
FINAL
2008
FINAL
2007
FINAL
2006
FINAL
2005
FINAL
2004
FINAL
2003
FINAL
2002
FINAL
2001
FINAL
2000
FINAL
1996
FINAL | 2026-11-16 21:40:12.947376 |
| 5 | 2026-10-26 21:40:16.831905 | 2026-10-26 21:40:16.831905 | 2026 | spill_cap_report | https://public.crohms.org/tmt/documents/ops/spill/caps/202607-Max+FOP.html | 51ccecbf1a61e4fe52df38cfb3234e7579b78dcea5333ffdbc98e60aa063fce0 | 0 | 0 | Fish Passage Max Spill - July 2026
Fish Passage Max Spill - July 2026
Date
Monitoring Stations
LWG
125%GC
LGS
125%GC
LMN
125%GC
IHR
125%GC
MCN
125%GC
JDA
125%GC
TDA
40%
BON
150 kcfs
07-01-2026
---
---
---
---
---
---
40%
150.0
07-02-2026
---
---
---
---
---
---
40%
150.0
07-03-2026
---
---
---
---
---
---
40%
150.0
07-04-2026
---
---
---
---
---
---
40%
150.0
07-05-2026
---
---
---
---
---
---
40%
150.0
07-06-2026
---
---
---
---
---
---
40%
150.0
07-07-2026
---
---
---
---
---
---
40%
150.0
07-08-2026
---
---
---
---
---
---
40%
150.0
07-09-2026
---
---
---
---
---
---
40%
150.0
07-10-2026
---
---
---
---
---
---
40%
150.0
07-11-2026
---
---
---
---
---
---
40%
150.0
07-12-2026
---
---
---
---
---
---
40%
150.0
07-13-2026
---
---
---
---
---
---
40%
150.0
07-14-2026
---
---
---
---
---
---
40%
150.0
07-15-2026
---
---
---
---
---
---
40%
150.0
07-16-2026
---
---
---
---
---
---
40%
150.0
07-17-2026
---
---
---
---
---
---
40%
150.0
07-18-2026
---
---
---
---
---
---
40%
150.0
07-19-2026
---
---
---
---
---
---
40%
150.0
07-20-2026
---
---
---
---
---
---
40%
150.0
07-21-2026
---
---
---
---
---
---
40%
150.0
07-22-2026
---
---
---
---
---
---
40%
150.0
07-23-2026
---
---
---
---
---
---
40%
150.0
07-24-2026
---
---
---
---
---
---
40%
150.0
07-25-2026
---
---
---
---
---
---
40%
150.0
07-26-2026
---
---
---
---
---
---
40%
150.0
07-27-2026
---
---
---
---
---
---
40%
150.0
07-28-2026
---
---
---
---
---
---
40%
150.0
07-29-2026
---
---
---
---
---
---
40%
150.0
07-30-2026
---
---
---
---
---
---
40%
150.0
07-31-2026
---
---
---
---
---
---
40%
150.0
Monthly Min
0.0
0.0
0.0
0.0
0.0
0.0
40%
150.0
Monthly Max
0.0
0.0
0.0
0.0
0.0
0.0
40%
150.0
Monthly Average
0.0
0.0
0.0
0.0
0.0
0.0
40%
150.0
Units in kcfs unless otherwise noted
Effective at 1600 hours between April 1 - August 31
Generated: Mon Aug 31 23:52:14 2026
--- indicates No Data | 2026-10-26 21:40:16.896674 |