Cipher Digital Stingray
Under Construction
Under Construction
Stingray is a Cipher Digital data center under construction at 110 SW 9001, Andrews, Texas. Cipher bought the 250-acre West Texas site in November 2024 with up to 100 MW of front-of-the-meter capacity, regulatory approvals and a facility extension agreement with Oncor. Subsidiary Stingray Compute LLC offered $810 million of notes in June 2026 to finance the facility; by August 2026 earthwork, grading, pad preparation and underground electrical work were underway. Cipher lists a further 200 MW Stingray expansion for 2030 or later.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 100 MW | Capacity basis unspecified | Reported | Exact Asset | — |
| Up to 100 MW of front-of-the-meter capacity with regulatory approvals and an Oncor facility extension agreement (November 2024); basis unspecified. | ||||
| 200 MW | Capacity basis unspecified | Reported | Stingray Expansion | — |
| Operator pipeline lists a 200 MW Stingray expansion with energization 2030+; basis unspecified. | ||||