Santee BESS is SDG&E’s 10 MW / 40 MWh battery beside its Santee Substation in San Diego County. The utility’s fact sheet describes a four-hour lithium iron phosphate system in twelve twenty-foot containers. EIA’s August 2026 preliminary inventory lists the unit as operating from January 2026, later than the project’s original 2024 target and subsequent construction schedules.
EIA plant 67118 · Inventory reporting month unavailable.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| 1 | Batteries | Operating | 10 | Unknown |
SDG&E’s project fact sheet specifies 10 MW / 40 MWh, a four-hour system using lithium iron phosphate batteries in twelve twenty-foot containers. It is located on SDG&E-owned property beside Santee Substation.
EIA’s August 2026 preliminary generator inventory records January 2026 as the operating month. Earlier July 2024 and Q1 2025 dates were project targets or estimates, rather than the current EIA-reported operating month.
Source: www.eia.gov exact-project record · as of 2026-08
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| 1 | 10 MW 10 MW summer | Batteries Electricity used for energy storage · BA | Jan 2026 | Operating |
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
SDG&E submitted Advice Letter 4290-E requesting approval of two EPC contracts with Stella Energy Solutions for 39.6 MW total of utility-owned energy storage, including the 10 MW Santee project.
| Largest reported plants | Capacity | State | |
|---|---|---|---|
| Palomar Energy | 559 MW | CA | |
| Miramar Energy Facility | 106 MW | CA | |
| Cuyamaca Peak Energy Plant | 48.7 MW | CA | |
| Fallbrook Energy Storage | 40 MW | CA | |
| Top Gun Energy Storage | 30 MW | CA | |
| Melrose BESS | 20 MW | CA | |
| Elliott Energy Storage | 10 MW | CA | |
| Boulevard Energy Storage | 10 MW | CA |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioSDG&E’s May 2025 ERRA testimony says Advice Letter 4290-E, covering Fallbrook Energy Storage 2 and Santee, was approved in December 2023. The earlier draft resolution estimated $110.4 million for the two-project package; that was not a Santee-only cost.
SDG&E fact sheet listed January 2024 as the project construction start date.
The CPUC-approved contractual commercial-operation date for the Santee BESS project. Later construction updates and workpaper forecasts indicate this target was not met.
SDG&E issued a second construction notification letter describing ongoing crew mobilization and primary construction and installation work. Anticipated schedule was ongoing through approximately Q1 2025.
EIA’s August 2026 preliminary inventory lists Santee generator 1 as operating, with January 2026 as its operating month. This monthly inventory record does not disclose a specific contractual commercial-operation day.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
SDG&E’s project fact sheet specifies 10 MW / 40 MWh, a four-hour system using lithium iron phosphate batteries in twelve twenty-foot containers. It is located on SDG&E-owned property beside Santee Substation.
EIA’s August 2026 preliminary generator inventory records January 2026 as the operating month. Earlier July 2024 and Q1 2025 dates were project targets or estimates, rather than the current EIA-reported operating month.
Santee BESS reports 10 MW battery storage of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Form 860M.
Santee BESS is a batteries facility in San Diego County, CA, participating in the CAISO market.
Santee BESS is in San Diego County, CA, inside the CAISO balancing area.
Santee BESS is operated by San Diego Gas & Electric Co according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
By capacity, Santee BESS ranks #488 of 1,061 operating plants of the same technology nationally. It ranks #154 of 272 in CA.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.