Natural Gas Fired Combined CycleNYISO · Orange Countyplant:plant-56940

CPV Valley Energy Center

CPV Valley, LLC - Orange County - NYISO

CPV Valley Energy Center is a 680-MW natural-gas-fired combined-cycle electric generating facility located in Wawayanda, Orange County, New York. The plant uses two Siemens SGT6-5000F gas turbines and one Siemens SST-5000 steam turbine, operating primarily on pipeline natural gas with ultra-low-sulfur distillate oil available as backup fuel. CPV Valley, LLC is the owner and operator; the facility is developed and managed by Competitive Power Ventures. The plant serves the Lower Hudson Valley reliability region and displaces less-efficient generation while supporting grid stability.

Overview

Key fields

Nameplate capacity
770.5 MW

Canonical EIA plant baseline.

Registry anchor
Plant 56940

plant-56940

Structured profile

Technology
Natural Gas Fired Combined Cycle
Operator
CPV Valley, LLC

Units and generators

Operating generator records and technology attributes reported through EIA-860.

GeneratorCapacityTechnologyOperationStatus
CTG1235 MW
175.8 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CT
May 2018Operating
CTG2235 MW
183.4 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CT
May 2018Operating
STG300.5 MW
295.1 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CA
May 2018Operating

Performance

Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.

Peer context

Technology capacity
770.5 MW
Natural Gas Fired Combined Cycle
National rank
#154
of 538 operating peers
NY rank
#5
of 39 operating peers

Monthly generation

Download CSV
Latest 12 months
4.56 TWh
Reported net generation
Latest report
Apr 2026
EIA-923 monthly filing
2025 capacity factor
70.0%
Using current reported nameplate capacity
May 2023: 209.7 GWh2023-05Jun 2023: 429.4 GWhJul 2023: 478 GWhAug 2023: 466.8 GWhSep 2023: 448.8 GWhOct 2023: 32.7 GWhNov 2023: 452.7 GWh2023-11Dec 2023: 484.6 GWhJan 2024: 485.9 GWhFeb 2024: 469.1 GWhMar 2024: 456.1 GWhApr 2024: 318.6 GWhMay 2024: 447.9 GWh2024-05Jun 2024: 435.7 GWhJul 2024: 469.2 GWhAug 2024: 461.5 GWhSep 2024: 454.7 GWhOct 2024: 294.4 GWhNov 2024: 229.3 GWh2024-11Dec 2024: 479.6 GWhJan 2025: 501.2 GWhFeb 2025: 464.7 GWhMar 2025: 472 GWhApr 2025: 455.2 GWhMay 2025: 267.4 GWh2025-05Jun 2025: 447.4 GWhJul 2025: 471.5 GWhAug 2025: 462.5 GWhSep 2025: 455.8 GWhOct 2025: 153.9 GWhNov 2025: 60.1 GWh2025-11Dec 2025: 513.7 GWhJan 2026: 505.1 GWhFeb 2026: 464.7 GWhMar 2026: 444 GWhApr 2026: 309.4 GWh2026-04

Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.

Grid and market context

Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.

Nearby substations

HIFLD infrastructure inventory
IN SERVICE · 138 kV
2.4 km
IN SERVICE · 138 kV
3.1 km
IN SERVICE
3.4 km
IN SERVICE · 69 kV
6.3 km
IN SERVICE · 69 kV
6.5 km

Commercial, land, and environmental record

Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.

Transactions and agreements

Development Phase
2013
NY regulatory materials describe CPV Valley as a proposed Lower Hudson Valley combined-cycle project in development stage; CPV intended to finance through non-recourse credit facilities and sponsor equity with a proposed June 1, 2016 commercial-operation target.
Competitive Power Ventures
documents.dps.ny.gov
Construction Start
Jul 2015
Skanska signed a $255 million construction contract with CPV; Skanska, Burns & McDonnell, and ECCO III Enterprises formed the EPC joint venture. Construction began in July 2015 with scheduled substantial completion in 2017.
$255MCompetitive Power Ventures · Skanska USA
skanska.com

Related parties and identifiers

Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.

Relationship graph

Drag organizations to explore the network. Select a node to pin its details and available page link.

AssetOwner / operatorContractorFinancier

Parties and identifiers

RelationshipEntityBasis
Operator / developer / asset managerCPV Group LPDeveloper, asset manager, and CPV corporate platform
Former ownerGlobal Infrastructure PartnersPredecessor corporate owner (2015–2021)
Owner / equity investorOPC Energy LtdSuccessor corporate owner (70% stake through acquisition)
Owner / equity investorDiamond Generating CorporationDevelopment and financing partner; 50% indirect owner
Parent companyMitsubishi CorporationUltimate parent of Diamond Generating Corporation
EPC contractor / construction contractorSkanska USALead EPC contractor (joint venture with Burns & McDonnell and ECCO III Enterprises)
Financier / equipment supplierSiemensGas and steam turbine OEM; project-finance lender
Grid selectionplant:plant-56940Canonical asset page /nyiso/assets/plant/cpv-valley-energy-center.

Reporting portfolio

EIA reporting entity
CPV Valley, LLC
Entity 56204
Operating portfolio
1 plants
1 states
Reported capacity
770.5 MW
Natural Gas Fired Combined Cycle

Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.

Timeline and sources

Project milestones and public references behind the asset profile.

Project timeline

  1. Development and pre-construction planningdocuments.d...

    NY regulatory materials describe CPV Valley as a proposed Lower Hudson Valley combined-cycle project in development stage; CPV intended to finance through non-recourse credit facilities and sponsor equity with a proposed June 1, 2016 commercial-operation target.

  2. Construction contract and startskanska.com

    Skanska signed a $255 million construction contract with CPV; Skanska, Burns & McDonnell, and ECCO III Enterprises formed the EPC joint venture. Construction began in July 2015 with scheduled substantial completion in 2017.

  3. Generators enter operationEIA-860

    EIA-860 lists generator CTG1, generator CTG2, generator STG with this operating date.

Common questions about CPV Valley Energy Center

Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.

How big is CPV Valley Energy Center?

CPV Valley Energy Center has a reported capacity of 770.5 MW. Source: EIA Form 860M.

What kind of plant is CPV Valley Energy Center?

CPV Valley Energy Center is a Natural Gas Fired Combined Cycle facility in Orange County, NY, participating in the NYISO market.

Where is CPV Valley Energy Center located?

CPV Valley Energy Center is in Orange County, NY, inside the NYISO balancing area.

Who operates CPV Valley Energy Center?

CPV Valley Energy Center is operated by CPV Valley, LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.

How much electricity does CPV Valley Energy Center generate?

CPV Valley Energy Center reported 4,555.3 GWh over the twelve months to 2026-04. Figures are net generation as filed to EIA-923.

How does CPV Valley Energy Center compare to other plants?

By capacity, CPV Valley Energy Center ranks #154 of 538 operating plants of the same technology nationally. It ranks #5 of 39 in NY.

Asset analyst
plant:plant-56940

Ask about CPV Valley Energy Center

Investigate technology, capacity, output, price behavior, ownership, and related facilities using this profile plus current grid data.