NuclearNYISO · Oswego Countyplant:plant-6110

James A. FitzPatrick Clean Energy Center

Constellation Energy Generation, LLC - Oswego County - NYISO

James A. FitzPatrick is a single-unit boiling-water nuclear reactor located in Scriba, Oswego County, New York, on the shores of Lake Ontario. Construction began in 1969, and the plant entered commercial operation on July 28, 1975. Originally developed and operated by the New York Power Authority in partnership with Niagara Mohawk Power Corporation, the facility was sold to Entergy Corporation in November 2000. Following a planned 2015 closure announcement, the New York Clean Energy Standard facilitated the plant's continued operation. Exelon subsequently transferred ownership to its subsidiary Exelon FitzPatrick, LLC in November 2017, and the plant was included in Constellation Energy when Exelon separated its generation business in February 2022. Constellation Energy Generation, LLC currently operates the facility. The plant's renewed NRC operating license (DPR-59, docket 50-333) expires October 17, 2034, with a subsequent license-renewal pathway available through 2054. The facility generates up to 842 MW of carbon-free electricity and is interconnected to the New York Power Authority transmission system at 345 kV.

Overview

Key fields

Nameplate capacity
883.3 MW

Canonical EIA plant baseline.

Registry anchor
Plant 6110

plant-6110

Structured profile

Technology
Nuclear
Operator
Constellation Energy Generation, LLC

Commercial, land, and environmental record

Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.

Transactions and agreements

Construction Start
1969
The New York Power Authority's official timeline states that construction began on the James A. FitzPatrick Nuclear Power Plant (820,000 kW) on the shores of Lake Ontario near Oswego.
Power Authority of the State of New York (NYPA)
nypa.gov
Commercial Operation
Jul 28, 1975
The James A. FitzPatrick Nuclear Power Plant entered commercial operation.
Power Authority of the State of New York (NYPA) · Niagara Mohawk Power Corporation
en.wikipedia.org
Closure Announcement
Nov 2, 2015
Entergy announced that FitzPatrick would be closed due to economic pressures, despite the operating license running through October 17, 2034.
Entergy Nuclear FitzPatrick, LLC / Entergy Nuclear Operations, Inc.
powermag.com
License Transfer
Nov 7, 2017
The NRC approved a direct transfer of the James A. FitzPatrick Renewed Facility Operating License DPR-59 and the associated Independent Spent Fuel Storage Installation (ISFSI) general license from Exelon Generation Company, LLC to its wholly owned subsidiary, Exelon FitzPatrick, LLC. Exelon Generation remained responsible for operation and maintenance.
Exelon Generation Company, LLC · Exelon FitzPatrick, LLC · U.S. Nuclear Regulatory Commission
nrc.gov
Corporate Separation
Feb 1, 2022
Exelon completed the separation of its competitive generation and customer-facing energy businesses into Constellation Energy, now an independent, publicly traded company. Constellation Energy Generation, LLC (formerly Exelon Generation Company, LLC) is now the owner and operator of James A. FitzPatrick. Exelon no longer retains ownership interest in Constellation.
Exelon Corporation · Constellation Energy Generation, LLC
investors.constellationenergy.com

Related parties and identifiers

Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.

Relationship graph

Drag organizations to explore the network. Select a node to pin its details and available page link.

AssetOwner / operatorMarket / regulatorOrganizationRelated asset

Parties and identifiers

RelationshipEntityBasis
Owner / operatorConstellation Energy Generation, LLCCurrent owner and licensee
Former owner / operatorEntergy Nuclear FitzPatrick, LLC / Entergy Nuclear Operations, Inc.Prior owner and operator
Former owner / operator / developerPower Authority of the State of New York (NYPA)Original developer and predecessor owner
RegulatorU.S. Nuclear Regulatory CommissionNuclear regulator
Transmission owner / interconnecting utilityNew York Power Authority (NYPA) / National GridTransmission owner and interconnection counterparty
Grid selectionplant:plant-6110Canonical asset page /nyiso/assets/plant/james-a-fitzpatrick-clean-energy-center.

Timeline and sources

Project milestones and public references behind the asset profile.

Project timeline

  1. Construction Begannypa.gov

    The New York Power Authority's official timeline states that construction began on the James A. FitzPatrick Nuclear Power Plant (820,000 kW) on the shores of Lake Ontario near Oswego.

  2. Commercial Operation Beganen.wikipedi...

    The James A. FitzPatrick Nuclear Power Plant entered commercial operation.

  3. Planned Closure Announcedpowermag.com

    Entergy announced that FitzPatrick would be closed due to economic pressures, despite the operating license running through October 17, 2034.

  4. Entergy-Exelon sale agreement announcedentergy.com

    Exelon Generation agreed to acquire ownership and assume operations of Entergy's James A. FitzPatrick Nuclear Power Plant under an agreement totaling $110 million. The transaction was facilitated by New York's Clean Energy Standard (CES), approved the same week, which recognizes the zero-emission attributes of nuclear power plants.

  5. Ownership transfer to Exelon completedentergy.com

    The transfer of James A. FitzPatrick from Entergy to Exelon Generation was completed. The plant's federal operating license was transferred, and Exelon assumed ownership and management of operations. Approximately 600 employees transferred to Exelon.

  6. License transferred to Exelon subsidiarynrc.gov

    The NRC approved a direct transfer of the James A. FitzPatrick Renewed Facility Operating License DPR-59 and the associated Independent Spent Fuel Storage Installation (ISFSI) general license from Exelon Generation Company, LLC to its wholly owned subsidiary, Exelon FitzPatrick, LLC. Exelon Generation remained responsible for operation and maintenance.

  7. Exelon separation: Constellation Energy becomes independentinvestors.c...

    Exelon completed the separation of its competitive generation and customer-facing energy businesses into Constellation Energy, now an independent, publicly traded company. Constellation Energy Generation, LLC (formerly Exelon Generation Company, LLC) is now the owner and operator of James A. FitzPatrick. Exelon no longer retains ownership interest in Constellation.

  8. NRC approves subsequent license-renewal exemptionfederalregi...

    The NRC issued an exemption in response to Constellation's December 7, 2023 request, allowing timely-renewal protection if Constellation submits a subsequent license-renewal application (SLRA) at least 3 years prior to the expiration of the existing operating license. If an acceptable SLRA is submitted by October 17, 2031, the current license will not expire until the NRC makes a final determination on the SLRA. The current license expires October 17, 2034.

Common questions about James A. FitzPatrick Clean Energy Center

Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.

How big is James A. FitzPatrick Clean Energy Center?

James A. FitzPatrick Clean Energy Center has a reported capacity of 883.3 MW. Source: EIA Form 860M.

What kind of plant is James A. FitzPatrick Clean Energy Center?

James A. FitzPatrick Clean Energy Center is a nuclear facility in Oswego County, NY, participating in the NYISO market.

Where is James A. FitzPatrick Clean Energy Center located?

James A. FitzPatrick Clean Energy Center is in Oswego County, NY, inside the NYISO balancing area.

Who operates James A. FitzPatrick Clean Energy Center?

James A. FitzPatrick Clean Energy Center is operated by Constellation Nuclear according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.

Asset analyst
plant:plant-6110

Ask about James A. FitzPatrick Clean Energy Center

Investigate technology, capacity, output, price behavior, ownership, and related facilities using this profile plus current grid data.