Pine Forest Solar I is a 500 MW batteries, solar photovoltaic plant in Hopkins County. Pine Forest Energy Center in Hopkins County, Texas, pairs 300 MW of solar generation with a 200 MW battery storage facility. Clearway Energy Group closed a bank financing and began construction in October 2024, with Blattner Energy leading construction, and brought the project online in February 2026. The solar output is backed by long-term virtual power purchase agreements with Dell Technologies and Universal Corporation, and Clearway Energy, Inc. agreed to invest upon commercial operations.
Mapped infrastructure geometry associated with this asset.
EIA plant 68906 · Inventory for Sep 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| PFBA | Batteries | Operating | 200 | 200 |
| PFPV | Solar Photovoltaic | Operating | 300 | Unknown |
| PFBA2 | Batteries | Under construction | 200 | Unknown |
Similar plants ranked by technology, capacity, and distance.
Current generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| PFBA | 200 MW 200 MW summer | Batteries BA | Oct 2025 | Operating |
| PFPV | 300 MW 300 MW summer | Solar Photovoltaic PV | Dec 2025 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Where the plant sits in ERCOT: its market, pricing node, utility territory and the network around it, each with how it is known.
The site also falls inside the Wood County Electric Coop, Inc service territory.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
$665 million bank-financed project.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
Cycles/day is discharged energy vs. usable capacity (~407 MWh). Capacity factor is avg discharge vs. peak.
Observed ERCOT settlement prices at PINEFRST_RN over 365 days (2025-11-24 to 2026-11-23).
The TB2 figure is a price benchmark, not revenue: it values one perfect-foresight cycle per day between the 2 cheapest and 2 dearest hours of each day, gross of round-trip losses, and excludes ancillary services and any physical dispatch constraint. It describes what this node’s price shape was worth over the window — it is not this asset’s realized capture, and no dispatch is assumed or modelled.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
EIA-860 lists generator PFBA with this operating date.
EIA-860 lists generator PFPV with this operating date.
300 MW solar and 200 MW storage.
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Pine Forest Solar I reports 200 MW battery storage + 300 MW solar of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Sep 2026.
Pine Forest Solar I is a Batteries, Solar Photovoltaic facility in Hopkins County, TX, participating in the ERCOT market.
Pine Forest Solar I is in Hopkins County, TX, inside the ERCOT balancing area.
Pine Forest Solar I is operated by Pine Forest Solar I, LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Pine Forest Solar I reported 465.6 GWh over the twelve months to 2026-08. Figures are net generation as filed to EIA-923.
By capacity, Pine Forest Solar I ranks #45 of 7,597 operating plants of the same technology nationally. It ranks #25 of 242 in TX.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.