Bright Stalk Wind Farm I
Bright Stalk Wind Farm I is a 205.2 MW onshore wind facility located in McLean County, Illinois, near Chenoa within the Chenoa, Yates, and Lawndale townships.
Bright Stalk Wind Farm I is a 205.2 MW onshore wind facility located in McLean County, Illinois, near Chenoa within the Chenoa, Yates, and Lawndale townships.
Canonical EIA plant baseline.
plant-57623
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| GEN1 | 205.2 MW 205.2 MW summer | Onshore Wind Turbine Wind · WT | Dec 2019 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
McLean County project overview identified Lexington Chenoa Wind Farm LLC as a wholly owned EDPR subsidiary, proposing up to 58 Vestas V136 turbines rated at 3.45 MW or 3.6 MW.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Salesforce announced a 15-year virtual power purchase agreement supporting 80 MW of the Bright Stalk Project. The project was owned and expected to be operated by EDPR, with completion scheduled for end of 2019.
EIA-860 lists generator GEN1 with this operating date.
Mortenson announced completion of construction. The project represented more than $300 million of capital investment; Mortenson was the civil contractor and Vestas supplied the V136 3.6 MW turbines.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Bright Stalk Wind Farm I has a reported capacity of 205.2 MW. Source: EIA Form 860M.
Bright Stalk Wind Farm I is a Onshore Wind Turbine facility in McLean County, IL, participating in the PJM market.
Bright Stalk Wind Farm I is in McLean County, IL, inside the PJM balancing area.
Bright Stalk Wind Farm I is operated by Lexington Chenoa Wind Farm LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Bright Stalk Wind Farm I reported 752.7 GWh over the twelve months to 2026-04. Figures are net generation as filed to EIA-923.
By capacity, Bright Stalk Wind Farm I ranks #227 of 1,362 operating plants of the same technology nationally. It ranks #14 of 57 in IL.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.