Operating 165 MWac solar photovoltaic facility in Spotsylvania County, Virginia, entered service December 2020. Owned by Highlander Solar Energy Station 1, LLC (100% owned by AES Corporation) and operated by AES Distributed Energy. Uses crystalline-silicon photovoltaic modules on single-axis tracking systems with 200.1 MWdc net capacity. Interconnects through the 500 kV Spotsylvania Substation and sells power into the PJM wholesale market. Part of the four-phase Spotsylvania Solar Energy Center portfolio (617 MWdc total).
Mapped infrastructure geometry associated with this asset.
EIA plant 62014 · Inventory for Aug 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| HLND1 | Solar Photovoltaic | Operating | 165 | Unknown |
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| HLND1 | 165 MW 165 MW summer | Solar Photovoltaic Solar · PV | Dec 2020 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
AES Corporation and Alberta Investment Management Corporation agreed to acquire FTP Power LLC (sPower) from Fir Tree Partners and minority owners for $853 million in cash plus assumption of $724 million in non-recourse debt.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
| Largest reported plants | Capacity | State | |
|---|---|---|---|
| Pleinmont Solar 2 | 240 MW | VA | |
| Buffalo Gap 2 Wind Farm | 232.5 MW | TX | |
| Prevailing Wind Park | 220 MW | SD | |
| Skipjack Solar Center | 175 MW | VA | |
| Buffalo Gap 3 Wind Farm | 170.2 MW | TX | |
| Highlander Solar Energy Station 1Current | 165 MW | VA | |
| Lancaster Area Battery | 127 MW | CA | |
| Buffalo Gap Wind Farm | 120.6 MW | TX |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioFir Tree Partners completed the sale of FTP Power LLC (sPower) to AES Corporation and Alberta Investment Management Corporation for approximately $1.6 billion in cash and assumed non-recourse debt.
Mortenson provided EPC services for the 165 MW Highlander photovoltaic plant; Brent Scarbrough & Company was the civil contractor; construction began late 2019 and was expected to complete by end of Q3 2020.
EIA-860 lists generator HLND1 with this operating date.
Highlander Solar Energy Station 1 (plant code 62014, generator HLND1) entered commercial operation; FERC in-service date of December 29, 2020.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Highlander Solar Energy Station 1 reports 165 MW solar of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Aug 2026.
Highlander Solar Energy Station 1 is a Solar Photovoltaic facility in Spotsylvania County, VA, participating in the PJM market.
Highlander Solar Energy Station 1 is in Spotsylvania County, VA, inside the PJM balancing area.
Highlander Solar Energy Station 1 is operated by AES Distributed Energy according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Highlander Solar Energy Station 1 reported 293.3 GWh over the twelve months to 2026-07. Figures are net generation as filed to EIA-923.
By capacity, Highlander Solar Energy Station 1 ranks #257 of 7,597 operating plants of the same technology nationally. It ranks #3 of 144 in VA.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.