Ask the Grid profiles 16 data centers served by AEP Ohio: 5 operating, 4 under construction, and 3 proposed or approved. The largest clusters are in New Albany (5), Hilliard (2), and Pataskala (2). The largest operators are Aligned Data Centers (2), Amazon Data Services, Inc. (2), and Meta (2).
| Asset | Reported | |
|---|---|---|
| 384 MWCapacity basis unspecified · Reported · campus | ||
The inventory contains published facility, campus, building, and phase records. Power figures describe the exact asset, including a campus record's own campus capacity, and retain their basis, scope, status, and date. Records at different scopes are not additive, and a published project does not establish an operating load.
Geographic directories use the state and city recorded for each asset. Organization groups preserve published names and roles. Utility groups use the utility named in the facility record; individual profiles distinguish service agreements from service-territory matches. Each profile carries the sources and dates behind its facts.