Grid

Data Center Power Capacity: What Public Records Show

Riot’s Rockdale site: 700 MW of gross power, 25 MW delivered to AMD, 25 MW contracted, up to 200 MW optioned. What each figure does and doesn’t mean.

October 14, 20267 min read

Revised October 19, 2026. Original publication date retained.

Horizontal bars for Riot’s Rockdale site: 700 MW gross site power, a separate 191 MW tenant lease, AMD options up to 200 MW, a 50 MW AMD contracted plan and 25 MW delivered to date.

A data center’s power numbers describe different things at different stages. Riot’s Rockdale, Texas site has been described with 700 MW of gross power capacity, 25 MW of delivered AMD critical IT load, and an eventual 200 MW AMD opportunity. Treating them as interchangeable makes a site look more ready than the documents establish.

This dossier follows the land purchase and the AMD deployment through company materials filed with the SEC. It answers what was owned, contracted and reported delivered, and names the evidence still missing before another tenant could count on a megawatt.

01

What does the public record establish about the site?

Riot’s January 16 announcement, filed as Exhibit 99.1 identifies a 200-acre Rockdale property in Milam County, Texas. It reports acquiring the underlying land, a 700 MW grid interconnection and an initial 25 MW critical-IT lease to AMD. These are company statements in a filed announcement, not a utility service agreement.

Cooling towers and equipment on the roof of a data center.
Data center cooling equipment.

Owning land establishes control of a site. It does not make every megawatt there available to a new tenant, because existing use, supply arrangements, connection conditions and conversion work are separate questions.

Mapped infrastructure works the same way. A nearby substation or transmission line is a good question to put to the serving provider; its presence does not establish an allocation to this parcel.

02

From contract to reported delivery

The original AMD agreement covered 25 MW of critical IT capacity with expansion rights. Riot’s April 30 filed presentation then showed a second 25 MW deployment, a 50 MW contracted plan rather than the full 200 MW opportunity.

A later financial-statement note on data-center operations reports that 5 MW of the first deployment was delivered in January and 20 MW in May. It describes the extra 25 MW in two expected phases, 10 MW in November 2026 and 15 MW in May 2027, and keeps conditional rights that could take AMD to 200 MW.

So the first 25 MW moved from plan to a company-reported completed deployment. The second 25 MW was still a future obligation at the record’s cutoff, and the remaining rights were never commissioned capacity.

Record / capacityWhat it establishesWhat it does not
200 acres, January filingCompany-reported acquisition of the underlying siteA new utility allocation to another tenant
700 MW gross power, January filingThe company’s stated site-level grid capacity700 MW of critical IT capacity
25 MW initial AMD deploymentLater filing reports 5 MW + 20 MW deliveredDelivery of the full possible 200 MW
25 MW additional AMD deploymentContracted expansion with stated future phasesThose phases already energized
Remaining conditional rightsPotential further AMD lease capacityExercised, built or delivered capacity

03

Why you can’t subtract IT load from gross power

Critical IT load is the computing equipment’s electrical demand. Gross site power also has to cover cooling, electrical losses and other infrastructure, so converting one to the other needs a defined facility boundary and an evidenced operating or design assumption.

The remainder isn’t automatically vacant either. The later filing describes a separate 191 MW critical-IT tenant lease, so 700 minus AMD’s 50 equals 650 MW “available” mixes units, ignores other commitments and assumes an allocation the documents never give.

A usable capacity ledger carries a unit and a status on every line: delivered critical IT, contracted future critical IT, conditional rights and gross site power each stay separate.

A team planning what to run on that power can check GPU rental benchmarks and capacity reservation terms for the separate question of compute pricing and availability.

04

How to turn open questions into a service request

A prospective tenant should bring a specific phase, demand profile and reliability requirement to the site owner and the serving provider, then ask for the contractual allocation at the point of delivery, the demand ramp, service conditions, curtailment provisions, required upgrades and dated milestones.

A technician working on a server rack.
A technician working on a server rack.

In ERCOT’s large-load process, the studied-question reference, page 6 covers site-control evidence and page 13 covers peak demand in the load commissioning plan. Those are process-specific requirements, not nationwide rules or a finding about this campus.

Owner / commercial team
Which space and power are already committed, the exact phase on offer, its allocation conditions, and the documents behind its delivery date.
Serving utility or transmission provider
The point of delivery, studied peak and ramp, required upgrades, service conditions and milestones for the proposed phase.
Tenant engineering team
Critical IT versus gross facility demand, redundancy, operating profile and tolerance for interruption, before comparing offered capacity.

05

What the record supports

The public record supports a site with identified land control, a company-stated interconnection, a reported completed first AMD deployment and a documented expansion path. That is more than a pin on a map and less than a verified promise of spare firm service for someone else.

For the ERCOT service question, use the large-load integration process, and keep generation queue records distinct from evidence of load service. This reads public filings through October 19, 2026, and later delivery filings should update each phase’s row rather than rewrite its earlier state.