Preferences
Appearance Dark Light Data centers in PJM · Page 6 · Ask the Grid
Ask the Grid profiles 415 data centers in PJM: 285 operating, 35 under construction, and 61 proposed or approved. The largest clusters are in Virginia (247), Illinois (48), and Ohio (42). Dominion Energy Virginia is the utility named for 163 of them. The largest operators are Amazon Web Services (54), Digital Realty (33), and Equinix (22).
profiled sites 415
operating 285
under construction 35
proposed or approved 61 Generation Data centers Storage Solar Wind NuclearAll markets CAISO CAISOERCOT ERCOTISO-NE ISO-NEMISO MISONYISO NYISOPJM PJMSPP SPP
Browse by state 10 states Alabama: no data centers Alaska: no data centers CyrusOne 11 data centers
Equinix Ashburn DC12 Equinix · Facility profile · Ashburn, VA
Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix Ashburn DC15 Equinix, Inc. · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · building
Equinix Ashburn DC21 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
11.875 MW Critical IT Load · Operating · facility · 2025-10
Equinix Ashburn DC4 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · building
Equinix Ashburn DC5 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
6 MW Energized Power · Operating · facility
Equinix Chicago CH1 Equinix · Facility profile · Chicago, IL Chicago, IL PJM
Unknown
Not disclosed No exact-asset power figure · facility
Equinix Chicago CH3 Equinix · Facility profile · Elk Grove Village, IL Elk Grove Village, IL PJM
Unknown
Not disclosed No exact-asset power figure · facility
Equinix Chicago CH7 Equinix · Facility profile · Westmont, IL Westmont, IL PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix Culpeper Campus (CU1-CU4) Equinix · Facility profile · Culpeper, VA Culpeper, VA PJM
Operating
Not disclosed No exact-asset power figure · campus
Equinix DC10 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · building
Equinix DC13 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix DC16 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · building
Equinix DC2 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix DC3 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix DC6 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix Manassas DC14 Equinix · Facility profile · Manassas, VA Manassas, VA PJM
Operating
4 MW Energized Power · Reported · facility
Equinix New York Secaucus NY4 Equinix · Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix New York Secaucus NY5 Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix NY1 Equinix · Facility profile · Newark, NJ Newark, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix NY2 Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix NY3 Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
15 MW Critical IT Load · Reported · facility
Equinix NY6 Equinix · Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
Not disclosed No exact-asset power figure · building
Equinix NY7 Equinix · Facility profile · North Bergen, NJ North Bergen, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix PH1 Philadelphia Equinix · Facility profile · Philadelphia, PA Philadelphia, PA PJM
Operating
Not disclosed No exact-asset power figure · facility
Equinix Washington DC DC1 Equinix · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
Not disclosed No exact-asset power figure · building
Evocative EWR1 Facility profile · Secaucus, NJ Secaucus, NJ PJM
Unknown
10 MW Energized Power · Reported · facility · 2022-09-29
Flex Data Center Reston Flex Data Center · Facility profile · Reston, VA Reston, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Flexential Cincinnati, Ohio Data Center Flexential · Facility profile · West Chester, OH West Chester, OH PJM
Operating
3.8 MW UPS capacity · Reported · facility
Flexential Philadelphia - Collegeville (PHL01) Flexential · Facility profile · Collegeville, PA Collegeville, PA PJM
Operating
7.2 MW Capacity basis unspecified · Reported · facility
Flexential Richmond Flexential · Facility profile · Richmond, VA Richmond, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Google Columbus Lockbourne Campus Google · Facility profile · Columbus, OH Columbus, OH PJM
Operating
Not disclosed No exact-asset power figure · campus
Google Lancaster Data Center Campus Google · Facility profile · Lancaster, OH Lancaster, OH PJM
Operating
96 MW Interconnection Request · Requested · campus · 2024-04-10
Google Leesburg Goose Landing Lane Data Center Facility profile · Leesburg, VA Leesburg, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Google Mango Farm Data Center Facility profile · Bristow, VA Bristow, VA PJM
Operating
Not disclosed No exact-asset power figure · facility
Google New Albany Data Center Campus Google · Facility profile · New Albany, OH New Albany, OH PJM
Operating
Not disclosed No exact-asset power figure · campus
Google Project Loch Data Center Campus at Watkins Centre Google · Facility profile · Chesterfield, VA Chesterfield, VA PJM
Approved
Not disclosed No exact-asset power figure · campus
Google Project Peanut Data Center Campus Google · Facility profile · Chester, VA Chester, VA PJM
Under Construction
Not disclosed No exact-asset power figure · campus
Google Wood Haven Technology Park Data Center Google · Facility profile · Roanoke, VA Roanoke, VA PJM
Proposed
40–80 MW Campus Gross Power · Reported · campus
H5 Data Centers Ashburn H5 Data Centers · Facility profile · Ashburn, VA Ashburn, VA PJM
Operating
42 MW Utility Service · Reported · facility · 2026-09-04
H5 Data Centers Cincinnati I H5 Data Centers · Facility profile · Cincinnati, OH Cincinnati, OH PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Cincinnati II H5 Data Centers · Facility profile · Cincinnati, OH Cincinnati, OH PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Cleveland H5 Data Centers · Facility profile · Cleveland, OH Cleveland, OH PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Herndon H5 Data Centers · Facility profile · Herndon, VA Herndon, VA PJM
Operating
Not disclosed No exact-asset power figure · campus
H5 Data Centers New Jersey (Secaucus) H5 Data Centers · Facility profile · Secaucus, NJ Secaucus, NJ PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Philadelphia H5 Data Centers · Facility profile · Philadelphia, PA Philadelphia, PA PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Pittsburgh H5 Data Centers · Facility profile · Pittsburgh, PA Pittsburgh, PA PJM
Operating
Not disclosed No exact-asset power figure · facility
H5 Data Centers Virginia Campus H5 Data Centers · Facility profile · Chantilly, VA Chantilly, VA PJM
Operating
23 MW Critical IT Load · Reported · campus
Hamilton Innovation Center City of Hamilton · Facility profile · Hamilton, OH Hamilton, OH PJM
Paused
45 MW Utility Service · Reported · facility
Hyperscale Data Michigan AI Data Center Campus Hyperscale Data, Inc. · Facility profile · Dowagiac, MI Dowagiac, MI PJM
Under Construction
Up to 52 MW Critical IT Load · Proposed · campus
Arizona: no data centers Colorado: no data centers Florida: no data centers Georgia: no data centers Indiana: 1 data centers Kansas: no data centers Maine: no data centers Massachusetts: no data centers Minnesota: no data centers New Jersey 30 data centers North Carolina: no data centers North Dakota: no data centers Oklahoma: no data centers Pennsylvania 36 data centers South Dakota: no data centers Texas: no data centers Wyoming: no data centers Connecticut: no data centers Missouri: no data centers West Virginia: no data centers Illinois 48 data centers New Mexico: no data centers Arkansas: no data centers California: no data centers Delaware: no data centers District of Columbia: 2 data centers Hawaii: no data centers Iowa: no data centers Kentucky: 1 data centers Maryland 7 data centers Michigan: 1 data centers Mississippi: no data centers Montana: no data centers New Hampshire: no data centers New York: no data centers Ohio 42 data centers Oregon: no data centers Tennessee: no data centers Utah: no data centers Virginia 247 data centers Washington: no data centers Wisconsin: no data centers Nebraska: no data centers South Carolina: no data centers Idaho: no data centers Nevada: no data centers Vermont: no data centers Louisiana: no data centers Rhode Island: no data centers
Browse by state or province 6
Development status
Approved 17
Expanding 4
Operating 281
Paused 1
Permitting 2
Proposed 42
Under Construction 35
Unknown 33 Sources and coverage The inventory contains published facility, campus, building, and phase records. Power figures describe the exact asset, including a campus record's own campus capacity, and retain their basis, scope, status, and date. Records at different scopes are not additive, and a published project does not establish an operating load.
Geographic directories use the state and city recorded for each asset. Organization groups preserve published names and roles. Utility groups use the utility named in the facility record; individual profiles distinguish service agreements from service-territory matches. Each profile carries the sources and dates behind its facts.