Ask the Grid
BriefingSPP

SPP's Grid Emergency Looked Very Different East and West

A series of federal emergency orders covered one integrated market. Ask the Grid data shows two balancing areas, a $2,054/MWh marginal-energy divide, and a resource stack that changed shape daily.

Craig Station power plant near Craig, Colorado
Craig Station was the largest physical site in DOE's July 26 resource exhibit, with 1,285 MW of summer-rated capability across three units. Photo: Jimmy / Wikimedia Commons, CC BY-SA 2.0.

From July 19 through August 10, the Southwest Power Pool moved from conservative operations to its highest level of emergency, then through three phases of federal emergency authority. The headline number was 4,845 MW: the summer-rated capability of 42 generating units that the Department of Energy authorized SPP to call beyond specified operating or environmental limits.

The more revealing number was $2,054/MWh. At 5:20 p.m. Central on July 20, during an Energy Emergency Alert 3 in SPP's Western balancing area, the system marginal-energy component was $2,091.10/MWh across 302 Western price locations and $37.10/MWh across 1,293 Eastern locations. One integrated market was producing two sharply different marginal-energy regimes.

One footprint, two marginal-energy prices
During the Western EEA3, the Western cohort's marginal-energy component was $2,054/MWh higher than the Eastern cohort's.
Western balancing area
$2,091.1
system marginal energy · $/MWh
302
price nodes
5th pct.
$1,943.5
Median LMP
$2,018.6
95th pct.
$2,127.3
Eastern balancing area
$37.1
system marginal energy · $/MWh
1,293
price nodes
5th pct.
-$4
Median LMP
$38.4
95th pct.
$41
Ask the Grid analysis of 1,595 deduplicated real-time SPP price locations at 5:20 p.m. CT on July 20, 2026. Cohorts are separated by their published system marginal-energy component. LMP bands show the inclusive 5th-to-95th-percentile range within each cohort.

The emergency started in the West#

SPP issued a conservative-operations advisory for its Western balancing area on July 19, effective July 20 at 11 a.m. Central. That afternoon, it escalated from an Energy Emergency Alert 1 at 4:38 p.m. to EEA3 at 5:07 p.m. EEA3 is SPP's highest emergency level: operating reserves had fallen below the required minimum, and firm-load interruption was possible. SPP later reported that it did not direct a controlled service interruption.

The factors SPP identified were familiar but simultaneous: high peak loads, widespread heat, generation outages, and low output from wind and other variable resources. Four days later, the West reached EEA2 again.

Federal authority shifted from West to both BAAs and back
The first federal order was West-only on July 20. A July 26 order expanded the authority to both balancing areas; its August 4 extension returned to the West alone.
Jul 20
West reaches EEA3
The advisory issued July 19 takes effect at 11 a.m. CT; EEA3 begins at 5:07 p.m. SPP reports no controlled interruption.
Jul 20
West-only federal order
DOE Order 202-26-36 applies to the Western balancing area through July 21.
Jul 24
West reaches EEA2
A second operating emergency begins at 8:04 p.m. CT, again without controlled interruption.
Jul 26
Both-area federal order
DOE Order 202-26-37 covers both SPP balancing areas through August 3.
Aug 4
West-only extension
Order 202-26-37A extends the authority through August 10 for the Western balancing area only.
SPP operating notices and DOE Orders 202-26-36, 202-26-37 and 202-26-37A. Times are Central. SPP reported no controlled service interruption during the July 20 or July 24 Western emergencies.
Across 1,595 observed locations, 302 Western nodes carried a $2,091.10/MWh system marginal-energy component while 1,293 Eastern nodes carried $37.10/MWh.
Open on the main map
1/3

The price divide was energy, not congestion#

At the July 20 snapshot, the two node cohorts separate on SPP's system marginal-energy component. Their congestion components were not what created the $2,054/MWh divide. The Western balancing area was short enough that its marginal energy cleared above $2,000/MWh while the East remained near $37/MWh.

Nodal prices within each balancing area still varied. The middle 90% of Western LMPs ran from $1,943.50 to $2,127.30/MWh. In the East, the same range ran from -$4 to $41/MWh. Treating either value as an SPP-wide price would erase the operational boundary that mattered most that afternoon.

The resource stack kept changing#

The first federal order was West-only on July 20. A July 26 order expanded the authority to both balancing areas; its August 4 extension returned to the West alone. The highest five-minute load during the July 26-August 3 order was 56,553 MW on July 27. That was not the day with the least wind. At the daily peak, wind supplied 10,309 MW, or 18.2% of load.

One day later, load was slightly lower at 54,286 MW, but wind output at the peak fell to 3,727 MW. Gas rose to 28,348 MW and coal to 15,637 MW. On August 3, the final day of the both-area order, wind supplied 18,978 MW, or 37% of peak load. The emergency authority was a contingency tool across a volatile period, not evidence that the system was equally scarce every hour.

Peak demand did not have one fuel mix
Wind supplied between 6.9% and 37.0% of daily peak load across the emergency period.
WindGasCoalSolar
Jul 19
51.7 GW
Jul 20
55.1 GW
Jul 21
53.8 GW
Jul 22
49.0 GW
Jul 23
47.1 GW
Jul 24
45.9 GW
Jul 25
53.8 GW
Jul 26
55.4 GW
Jul 27
56.6 GW
Jul 28
54.3 GW
Jul 29
53.4 GW
Jul 30
51.0 GW
Jul 31
50.8 GW
Aug 1
44.5 GW
Aug 2
47.7 GW
Aug 3
51.3 GW
Aug 4
49.8 GW
Aug 5
49.0 GW
Aug 6
51.0 GW
Aug 7
50.7 GW
Aug 8
51.1 GW
Aug 9
53.4 GW
Aug 10
55.8 GW
56.55 GW
window high · Jul 27
6.9%
wind at peak · Jul 28
37.0%
wind at peak · Aug 3
For each day from July 19 through August 10, Ask the Grid selected the highest deduplicated five-minute SPP system-load interval and joined the latest fuel-mix observation at that timestamp. The colored stack shows wind, gas, coal and solar; other fuels account for the remaining load.

The order named a concentrated plant portfolio#

DOE's July 26 resource exhibit listed 42 units at 13 physical sites in Colorado, Wyoming, Nebraska and Missouri. Six Tri-State Generation and Transmission plants accounted for 3,069 MW, 63% of the summer-rated capability on the list. Laramie River Station and Craig Station together represented half of the total.

The named resource list was concentrated in six Tri-State plants
DOE listed 42 units at 13 physical sites, totaling 4,845.12 MW of summer-rated capability.
Tri-State G&T6 sites
3.07 GW
City Utilities of Springfield3 sites
838 MW
Platte River Power Authority1 site
660.8 MW
Colorado Springs Utilities2 sites
204.98 MW
City of Grand Island1 site
72.34 MW
13 physical sites
Craig Station
CO1.28 GW
Laramie River Station
WY1.14 GW
Rawhide Energy Station
CO660.8 MW
John Twitty Energy Center
MO577 MW
J.M. Shafer
CO284 MW
James River Power Station
MO161 MW
South Plant
CO148.98 MW
Frank Knutson
CO130 MW
Limon
CO130 MW
Burlington
CO100 MW
McCartney Generating Station
MO100 MW
C.W. Burdick
NE72.34 MW
Ray D. Nixon
CO56 MW
42
listed units
13
physical sites
4.85 GW
summer rating
Summer ratings from DOE Order 202-26-37, grouped by physical plant and listed utility. Dual-fuel rows for C.W. Burdick are counted once. The 4,845.12 MW total is listed summer-rated capability, not measured dispatch during the order.

Those megawatts describe the units SPP was authorized to dispatch under the order. They are not a measure of how much emergency generation ran. DOE required SPP to submit daily notices identifying every specified resource that used the order's allowances. As of publication, the public DOE page contained no daily notices identifying an activated resource.

Backup generation was authorized, not documented as used#

The order contained a separate provision for data centers, hyperscalers and other large industrial or commercial loads. SPP could direct auxiliary, standby, battery or other backup generation resources at those sites to operate as a last resort before EEA3, or during EEA3, when needed to maintain reliability. Critical facilities were excluded.

That provision turned behind-the-meter flexibility into an explicit reliability resource. It did not establish that a data center started a generator. The order required daily reporting for any backup resource that used the authority. As of publication, the public DOE page contained no daily notices identifying an activated backup resource.

The distinction matters for operators. A large load's location, telemetry, curtailment rights, transfer sequence, on-site fuel and emissions limits are no longer peripheral facility details when an operator can call that flexibility in an emergency. SPP is implementing its accelerated High Impact Large Load process. The July orders show the operational terms that will determine whether a project is merely large or genuinely useful to the grid.

What decision-makers should take from July#

For large-load developers, the commercial value of flexibility depends on where the project connects and whether SPP can observe and control it. A curtailment promise without telemetry, fuel assurance or enforceable operating rights is not the same resource during an EEA3.

For generators, the order's list is a map of locational reliability value. Summer capability, environmental constraints and startup availability can matter more than annual energy production during a short emergency window.

For SPP and regulators, East and West need to be evaluated as distinct operating systems even when they share an organization. Publishing the required daily resource notices would show which federal allowances were actually used and which remained insurance.

Ask the Grid analyzed deduplicated five-minute system load, fuel mix and real-time nodal prices from July 19 through August 10. Daily peak fuel mixes use the latest ingested observation for each timestamp. The July 20 price snapshot contains 1,595 locations and separates the two published marginal-energy components before calculating each cohort's LMP distribution. DOE resource totals use summer ratings in the July 26 exhibit; dual-fuel rows are counted once.

The figures are frozen at publication. Open SPP on the live map to inspect current plants, prices and grid conditions.

Share this story#

Historical SPP map showing the East-West emergency price split, shareable chart card
01Historical SPP map showing the East-West emergency price split
Craig Station and the 4.85 GW federal-order portfolio, shareable chart card
02Craig Station and the 4.85 GW federal-order portfolio
SPP peak load and wind share from July 19 through August 10, shareable chart card
03SPP peak load and wind share from July 19 through August 10
SPP East and West price ranges shown on one common scale, shareable chart card
04SPP East and West price ranges shown on one common scale
Four export-ready cards summarize the East-West price split, federal resource authority, changing peak fuel mix and a common-scale price comparison.