Stream Data Centers 5 data centers
H5 Data Centers San Antonio — 100 Taylor Street H5 Data Centers · Facility profile · San Antonio, TX
San Antonio, TX ERCOT
Operating
4.5 MW Energized Power · Operating · facility
Houston 2 Data Center Data Foundry · Facility profile · Houston, TX Houston, TX ERCOT
Operating
60 MW Campus Gross Power · Reported · campus
Houston I Facility profile · The Woodlands, TX The Woodlands, TX ERCOT
Operating
7.8 MW Critical IT Load · Reported · facility
HTX1 – Houston Data Center Serverfarm · Facility profile · Hockley, TX Hockley, TX ERCOT
Operating
410 MW Critical IT Load · Reported · building
Hut 8 Beacon Point Hut 8 · Facility profile · Robstown, TX Robstown, TX ERCOT
Under Construction
1,000 MW Utility Service · Reported · campus
IREN Sweetwater 2 IREN · Facility profile · Hamlin, TX Hamlin, TX ERCOT
Under Construction
600 MW Capacity basis unspecified · Reported · facility
LightEdge Austin I LightEdge · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
LightEdge Austin II LightEdge · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Lincoln Red Oak Data Center Campus Lincoln Property Company · Facility profile · Red Oak, TX Red Oak, TX ERCOT
Proposed
Up to 384 MW Critical IT Load · Reported · campus
LOGIX Austin Data Center LOGIX Fiber Networks · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
Lowe's Data Center Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Lumen Austin 1 Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Lumen Austin 3 Lumen Technologies · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Lumen Dallas 1 Data Center Lumen Technologies · Facility profile · Dallas, TX Dallas, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Lumen San Antonio 2 Lumen Technologies · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
MARA Granbury Data Center MARA Holdings · Facility profile · Granbury, TX Granbury, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Mesones Prime Data Center Campus Prominent Property Group · Facility profile · Jarrell, TX Jarrell, TX ERCOT
Proposed
About 264 MW Capacity basis unspecified · Target · campus
Meta Fort Worth Data Center Meta · Facility profile · TX TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
Microsoft Castroville SAT89-90 Data Center Microsoft · Facility profile · Castroville, TX Castroville, TX ERCOT
Under Construction
Not disclosed No exact-asset power figure · campus
Microsoft Chevron/SN7 Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Microsoft Lambda Drive Datacenter Campus Microsoft · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · campus
Microsoft San Antonio SN1 and SN2 Data Center Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Microsoft SAT14 Data Center Microsoft · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Unknown
Not disclosed No exact-asset power figure · facility
Netrality Houston 1301 Fannin Netrality · Facility profile · Houston, TX Houston, TX ERCOT
Operating
26 MW Utility Service · Reported · building · 2026-03-02
Nexus Data Center Hubbard Nexus Hubbard Power, LLC · Facility profile · Hubbard, TX Hubbard, TX ERCOT
Under Construction
About 7,700 MW Capacity basis unspecified · Proposed · campus
Nscale Ward County Data Center Nscale · Facility profile · Barstow, TX Barstow, TX ERCOT
Operating
234 MW Capacity basis unspecified · Reported · facility · 2025-10-14
NTT Garland Campus NTT DATA · Facility profile · Garland, TX Garland, TX ERCOT
Operating
Not disclosed No exact-asset power figure · campus
NTT Lancaster TX10 Data Center Campus (Project Orange) NTT Global Data Centers Americas, Inc. · Facility profile · Lancaster, TX Lancaster, TX ERCOT
Approved
252 MW Capacity basis unspecified · Proposed · campus
Oppidan Connect Temple Data Center Oppidan · Facility profile · Temple, TX Temple, TX ERCOT
Under Construction
14 MW Contracted Power · Contracted · facility
Poolside Project Horizon Data Center Campus Poolside, Inc · Facility profile · Pecos, TX Pecos, TX ERCOT
Proposed
7,000+ MW Capacity basis unspecified · Reported · campus
PowerHouse Grand Prairie Data Center Campus Prairie Ridge Phase 1 Owner LP · Facility profile · Midlothian, TX Midlothian, TX ERCOT
Proposed
Up to 1,800 MW Utility Service · Proposed · campus
PowerHouse Irving Data Center Campus PowerHouse Data Centers · Facility profile · Irving, TX Irving, TX ERCOT
Under Construction
Up to 201 MW Utility Service · Proposed · campus
QTS Fort Worth 1 Quality Technology Services (QTS) · Facility profile · Fort Worth, TX Fort Worth, TX ERCOT
Expanding
70 MW Critical IT Load · Reported · campus
QTS Irving 1 QTS · Facility profile · Irving, TX Irving, TX ERCOT
Unknown
Not disclosed No exact-asset power figure · campus
QTS San Antonio 2 Data Center Campus Quality Technology Services (QTS) · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
27.6 MW Critical IT Load · Operating · campus · 2021-01-01
Raeden Jacinto City Inference Data Center IRGRA · Facility profile · Houston, TX Houston, TX ERCOT
Proposed
50 MW Capacity basis unspecified · Proposed · campus
Rice Data Center William Marsh Rice University · Facility profile · Houston, TX Houston, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Riot Platforms Corsicana Campus Riot Platforms · Facility profile · Corsicana, TX Corsicana, TX ERCOT
Expanding
1,000 MW Capacity basis unspecified · Reported · campus
Riot Rockdale Riot Platforms, Inc. · Facility profile · Thorndale, TX Thorndale, TX ERCOT
Operating
345 MW Contracted Power · Contracted · campus · 2025-12-31
Rowan Project Cinco Data Center Campus Rowan Cinco LLC · Facility profile · Medina, TX Medina, TX ERCOT
Under Construction
300 MW Capacity basis unspecified · Under Construction · campus
Rowan Project Stampede Data Center Campus Rowan Digital Infrastructure · Facility profile · Temple, TX Temple, TX ERCOT
Under Construction
300 MW Capacity basis unspecified · Reported · campus
Rowan Project Temple Data Center Campus Rowan · Facility profile · Temple, TX Temple, TX ERCOT
Under Construction
300 MW Capacity basis unspecified · Under Construction · campus
Sabey San Marcos Data Center Campus Sabey Data Centers · Facility profile · San Marcos, TX San Marcos, TX ERCOT
Proposed
Not disclosed No exact-asset power figure · campus
SAT82 Data Center Microsoft · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Approved
Not disclosed No exact-asset power figure · building
SB Energy Cosmos Technology Campus (HighPoint 2222) Facility profile · Austin, TX Austin, TX ERCOT
Under Construction
About 50 MW Critical IT Load · Under Construction · campus
SB Energy Milam Data Center Campus SB Energy · Facility profile · Burlington, TX Burlington, TX ERCOT
Under Construction
About 753 MW Critical IT Load · Under Construction · campus
SDC Austin Sabey Data Centers · Facility profile · Round Rock, TX Round Rock, TX ERCOT
Under Construction
84 MW Critical IT Load · Reported · campus
Skybox Hutto 2 (Building 2) Hutto Data Center Campus, LLC · Facility profile · Hutto, TX Hutto, TX ERCOT
Under Construction
Not disclosed No exact-asset power figure · building
Skybox PowerCampus Dallas Data Center Google · Facility profile · Lancaster, TX Lancaster, TX ERCOT
Under Construction
Up to 300 MW Campus Gross Power · Proposed · campus
Approved 8
Closed 1
Expanding 9
Operating 100
Proposed 15
Under Construction 27
Unknown 10 Sources and coverage The inventory contains published facility, campus, building, and phase records. Power figures describe the exact asset, including a campus record's own campus capacity, and retain their basis, scope, status, and date. Records at different scopes are not additive, and a published project does not establish an operating load.
Geographic directories use the state and city recorded for each asset. Organization groups preserve published names and roles. Utility groups use the utility named in the facility record; individual profiles distinguish service agreements from service-territory matches. Each profile carries the sources and dates behind its facts.